Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2009 |
Principal Product | Liquid and solid CO2 |
NAICS | 325120 - Industrial Gas Manufacturing |
SIC | 2813 - Industrial Gases |
Sales | $10,000,000-$50,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 112,500 |
Annual Production | 405,000,000 Pounds |
Production Hrs. Annual | 8,600 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,961,435 | 46,452,000 | kWh | $0.04 |
Electricity Demand | $1,087,389 | 77,791 | kW-months/year | $13.98 |
Electricity Fees | $38,628 | - | $ | - |
Natural Gas | $11,423 | 1,410 | MMBtu | $8.10 |
TOTAL ENERGY COSTS | $3,098,875 | |||
RECOMMENDED SAVINGS* | $43,961 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Water Consumption | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $22,190 Cost: $6,149 |
$15,177 | 359,480 | $7,013 | 502 | - | - | - | - | - | - | - | - |
$15,177 359,480 kWh |
$7,013 502 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $5,639 Cost: $7,629 |
$3,859 | 91,408 | $1,780 | 127 | - | - | - | - | - | - | - | - |
$3,859 91,408 kWh |
$1,780 127 kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $6,706 Cost: $19,737 |
$5,239 | 124,085 | $2,421 | 173 | - | - | $(-1,358) | - | $404 | - | - | - |
$5,239 124,085 kWh |
$2,421 173 kW-months/year |
- - MMBtu |
$(-1,358) - $ |
$404 - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $4,909 Cost: $6,600 |
- | - | - | - | $4,909 | 606 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$4,909 606 MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $4,517 Cost: $3,850 |
$(-27) | (-642) | $(-13) | (-12) | - | - | - | - | - | - | $4,557 | - |
$(-27) (-642) kWh |
$(-13) (-12) kW-months/year |
- - MMBtu |
- - $ |
- - $ |
$4,557 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $43,961 Cost: $43,965 |
$24,248 | 574,331 | $11,201 | 790 | $4,909 | 606 | $(-1,358) | - | $404 | - | $4,557 | - | $24,248 574,331 kWh |
$11,201 790 kW-months/year |
$4,909 606 MMBtu |
$(-1,358) - $ |
$404 - $ |
$4,557 - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
- - $ |
- - Tgal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | $ | $ | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Water Consumption | Electricity Usage | Electricity Demand | Natural Gas | Personnel Changes | Ancillary Material Cost | Water Consumption |