Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2012 |
Principal Product | Museum |
NAICS | 712110 - Museums |
SIC | 8412 - Museums And Art Galleries |
Sales | <$500,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 72,000 |
Annual Production | 1 Units |
Production Hrs. Annual | 3,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $93,175 | 1,382,016 | kWh | $0.07 |
Electricity Demand | $53,251 | 3,455 | kW-months/year | $15.41 |
Natural Gas | $42,171 | 4,516 | MMBtu | $9.34 |
TOTAL ENERGY COSTS | $188,597 | |||
RECOMMENDED SAVINGS* | $58,142 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $36,712 Cost: $21,000 |
$10,525 | 24,876 | $33,195 | - | - | - | $(-7,008) | (-283) | - | - | - | - |
$10,525 24,876 kWh |
$33,195 - kW-months/year |
- - MMBtu |
$(-7,008) (-283) MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7211 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS |
Savings: $1,450 Cost: $3,000 |
$672 | 10,196 | $778 | 45 | - | - | - | - | - | - | - | - |
$672 10,196 kWh |
$778 45 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $598 Cost: $1,000 |
- | - | - | - | $598 | 64 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$598 64 MMBtu |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4132 USE DEIONIZED WATER IN UPSTREAM RINSE TANKS |
Savings: $4,110 Cost: $5,000 |
- | - | - | - | - | - | - | - | $4,110 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
$4,110 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $1,077 Cost: - |
$1,077 | 16,349 | - | - | - | - | - | - | - | - | - | - |
$1,077 16,349 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,330 Cost: $600 |
$664 | 10,080 | $696 | 40 | - | - | - | - | - | - | $(-30) | - |
$664 10,080 kWh |
$696 40 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
$(-30) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $650 Cost: $1,080 |
$215 | 3,264 | $77 | 4 | - | - | - | - | - | - | $358 | - |
$215 3,264 kWh |
$77 4 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
$358 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $240 Cost: $352 |
$240 | 3,636 | - | - | - | - | - | - | - | - | - | - |
$240 3,636 kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $7,228 Cost: $16,470 |
$3,404 | 51,659 | $3,548 | 205 | - | - | - | - | - | - | $276 | - |
$3,404 51,659 kWh |
$3,548 205 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
$276 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $4,747 Cost: $16,220 |
$1,186 | 17,996 | $2,483 | 144 | - | - | - | - | - | - | $1,078 | - |
$1,186 17,996 kWh |
$2,483 144 kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
$1,078 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $58,142 Cost: $64,722 |
$17,983 | 138,056 | $40,777 | 438 | $598 | 64 | $(-7,008) | (-283) | $4,110 | - | $1,682 | - | $17,983 138,056 kWh |
$40,777 438 kW-months/year |
$598 64 MMBtu |
$(-7,008) (-283) MMBtu |
$4,110 - $ |
$1,682 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Fuel Oil #2 | Administrative Changes | Ancillary Material Cost |