IAC Assessment: NC0456
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0456
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2012
Principal Product Specialty Chemicals
NAICS 325199 - All Other Basic Organic Chemical Manufacturing
SIC 2869 - Industrial Organic Chemicals, Nec
Sales $10,000,000-$50,000,000
# of Employees 75
Plant Area (Sq.Ft.) 62,000
Annual Production 20,000,000 Pounds
Production Hrs. Annual 8,600
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $214,158 5,754,228 kWh $0.04
Electricity Demand $88,177 9,361 kW-months/year $9.42
Electricity Fees $151 - $ -
Natural Gas $1,325,221 264,649 MMBtu $5.01
TOTAL ENERGY COSTS $1,627,707
RECOMMENDED SAVINGS* $105,779 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $35,235
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$36,693
Cost:
$65,000
- - - - $36,693 7,280 - - - - -
-
kWh
-
-
kW-months/year
$36,693
7,280
MMBtu
-
-
$
-
-
$
02: 2.2113 REPAIR OR REPLACE STEAM TRAPS Savings:
$34,238
Cost:
$5,500
- - - - $42,585 8,500 $(-667) - $(-7,680) - -
-
kWh
-
-
kW-months/year
$42,585
8,500
MMBtu
$(-667)
-
$
$(-7,680)
-
$
03: 2.1243 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER Savings:
$28,806
Cost:
$60,000
- - - - $28,806 5,750 - - - - -
-
kWh
-
-
kW-months/year
$28,806
5,750
MMBtu
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$997
Cost:
$100
$1,061 28,516 $376 40 - - $(-200) - $(-240) - $1,061
28,516
kWh
$376
40
kW-months/year
-
-
MMBtu
$(-200)
-
$
$(-240)
-
$
05: 2.6221 USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY Savings:
$5,045
Cost:
$5,000
$5,045 135,553 - - - - - - - - $5,045
135,553
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$105,779
Cost:
$135,600
$6,106 164,069 $376 40 $108,084 21,530 $(-867) - $(-7,920) - $6,106
164,069
kWh
$376
40
kW-months/year
$108,084
21,530
MMBtu
$(-867)
-
$
$(-7,920)
-
$
TOTAL IMPLEMENTED Savings:
$35,235
Cost:
$5,600
$1,061 28,516 $376 40 $42,585 8,500 $(-867) - $(-7,920) - $1,061
28,516
kWh
$376
40
kW-months/year
$42,585
8,500
MMBtu
$(-867)
-
$
$(-7,920)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Personnel Changes Ancillary Material Cost