IAC Assessment: NC0457
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0457
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2012
Principal Product Escalators
NAICS 333921 - Elevator and Moving Stairway Manufacturing
SIC 3534 - Elevators And Moving Stairways
Sales $10,000,000-$50,000,000
# of Employees 150
Plant Area (Sq.Ft.) 150,000
Annual Production 500 Pieces
Production Hrs. Annual 2,500
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $157,212 3,098,000 kWh $0.05
Electricity Demand $89,827 10,588 kW-months/year $8.48
Natural Gas $85,902 9,895 MMBtu $8.68
TOTAL ENERGY COSTS $332,941
RECOMMENDED SAVINGS* $27,998 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,365
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,926
Cost:
$7,711
$1,196 23,535 $942 113 - - $(-212) - $1,196
23,535
kWh
$942
113
kW-months/year
-
-
MMBtu
$(-212)
-
$
02: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$415
Cost:
$525
$415 8,187 - - - - - - $415
8,187
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.7292 LOWER CEILING TO REDUCE CONDITIONED SPACE Savings:
$19,472
Cost:
$40,000
$7,520 148,033 $11,952 1,431 - - - - $7,520
148,033
kWh
$11,952
1,431
kW-months/year
-
-
MMBtu
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$508
Cost:
$400
$284 5,595 $224 27 - - - - $284
5,595
kWh
$224
27
kW-months/year
-
-
MMBtu
-
-
$
05: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$3,516
Cost:
-
$1,965 38,679 $1,551 186 - - - - $1,965
38,679
kWh
$1,551
186
kW-months/year
-
-
MMBtu
-
-
$
06: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS Savings:
$2,161
Cost:
$2,000
- - - - $2,161 249 - - -
-
kWh
-
-
kW-months/year
$2,161
249
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$27,998
Cost:
$50,636
$11,380 224,029 $14,669 1,757 $2,161 249 $(-212) - $11,380
224,029
kWh
$14,669
1,757
kW-months/year
$2,161
249
MMBtu
$(-212)
-
$
TOTAL IMPLEMENTED Savings:
$6,365
Cost:
$8,636
$3,860 75,996 $2,717 326 - - $(-212) - $3,860
75,996
kWh
$2,717
326
kW-months/year
-
-
MMBtu
$(-212)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Ancillary Material Cost