Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2012
Principal Product Automotive throttle assemblies
NAICS 336310 - Motor Vehicle Gasoline Engine and Engine Parts Manufacturing
SIC 3592 - Carburetors, Pistons, Rings, Valves
Sales $50,000,000-$100,000,000
# of Employees 330
Plant Area (Sq.Ft.) 300,000
Annual Production 900,000 Pieces
Production Hrs. Annual 4,600
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $719,537 15,892,600 kWh $0.05
Electricity Demand $530,293 30,994 kW-months/year $17.11
TOTAL ENERGY COSTS $1,249,830
RECOMMENDED SAVINGS* $88,173 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $83,375
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$25,477
Cost:
$67,898
$13,118 289,763 $12,109 756 - - $250 - $13,118
289,763
kWh
$12,109
756
kW-months/year
-
-
$
$250
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$44,453
Cost:
$152,640
$21,500 474,922 $19,848 1,239 - - $3,105 - $21,500
474,922
kWh
$19,848
1,239
kW-months/year
-
-
$
$3,105
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,925
Cost:
$8,552
$5,061 111,803 $4,673 292 - - $191 - $5,061
111,803
kWh
$4,673
292
kW-months/year
-
-
$
$191
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,710
Cost:
$4,085
$1,106 24,426 $1,021 64 - - $583 - $1,106
24,426
kWh
$1,021
64
kW-months/year
-
-
$
$583
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,052
Cost:
$1,980
$329 7,260 $465 29 - - $258 - $329
7,260
kWh
$465
29
kW-months/year
-
-
$
$258
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,036
Cost:
$624
$306 6,763 $149 9 - - $581 - $306
6,763
kWh
$149
9
kW-months/year
-
-
$
$581
-
$
07: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$222
Cost:
$300
$222 4,912 - - - - - - $222
4,912
kWh
-
-
kW-months/year
-
-
$
-
-
$
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,985
Cost:
$600
$1,864 41,179 $1,721 107 $(-300) - $(-300) - $1,864
41,179
kWh
$1,721
107
kW-months/year
$(-300)
-
$
$(-300)
-
$
09: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE Savings:
$313
Cost:
$750
$230 5,040 $83 5 - - - - $230
5,040
kWh
$83
5
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$88,173
Cost:
$237,429
$43,736 966,068 $40,069 2,501 $(-300) - $4,668 - $43,736
966,068
kWh
$40,069
2,501
kW-months/year
$(-300)
-
$
$4,668
-
$
TOTAL IMPLEMENTED Savings:
$83,375
Cost:
$230,740
$41,995 927,619 $38,434 2,399 $(-300) - $3,246 - $41,995
927,619
kWh
$38,434
2,399
kW-months/year
$(-300)
-
$
$3,246
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost