Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2012 |
Principal Product | Cigarette packing machines |
NAICS | 333249 - Other Industrial Machinery Manufacturing |
SIC | 3559 - Special Industry Machinery, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 164 |
Plant Area (Sq.Ft.) | 123,000 |
Annual Production | 10 Pieces |
Production Hrs. Annual | 3,500 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $111,736 | 1,431,136 | kWh | $0.08 |
Electricity Demand | $23,220 | 5,077 | kW-months/year | $4.57 |
Electricity Fees | $4,614 | - | $ | - |
Natural Gas | $30,880 | 2,380 | MMBtu | $12.97 |
TOTAL ENERGY COSTS | $170,450 | |||
RECOMMENDED SAVINGS* | $41,357 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $37,235 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $146 Cost: $652 |
$121 | 1,544 | $24 | 5 | - | - | $1 | - |
$121 1,544 kWh |
$24 5 kW-months/year |
- - MMBtu |
$1 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $290 Cost: $1,265 |
$144 | 1,840 | $101 | 22 | - | - | $45 | - |
$144 1,840 kWh |
$101 22 kW-months/year |
- - MMBtu |
$45 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $3,485 Cost: $18,400 |
$2,321 | 29,722 | $1,164 | 255 | - | - | - | - |
$2,321 29,722 kWh |
$1,164 255 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,208 Cost: $1,180 |
$554 | 7,098 | $45 | 10 | - | - | $609 | - |
$554 7,098 kWh |
$45 10 kW-months/year |
- - MMBtu |
$609 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $448 Cost: $525 |
$448 | 5,744 | - | - | - | - | - | - |
$448 5,744 kWh |
- - kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $347 Cost: $1,200 |
- | - | - | - | $347 | 27 | - | - |
- - kWh |
- - kW-months/year |
$347 27 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $245 Cost: $100 |
$204 | 2,611 | $41 | 9 | - | - | - | - |
$204 2,611 kWh |
$41 9 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $459 Cost: $300 |
$406 | 5,200 | $53 | 12 | - | - | - | - |
$406 5,200 kWh |
$53 12 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7224 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS |
Savings: $34,729 Cost: $15,000 |
$24,209 | 310,059 | $(-974) | (-213) | $11,494 | 886 | - | - |
$24,209 310,059 kWh |
$(-974) (-213) kW-months/year |
$11,494 886 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $41,357 Cost: $38,622 |
$28,407 | 363,818 | $454 | 100 | $11,841 | 913 | $655 | - | $28,407 363,818 kWh |
$454 100 kW-months/year |
$11,841 913 MMBtu |
$655 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $37,235 Cost: $17,757 |
$25,942 | 332,256 | $(-811) | (-177) | $11,494 | 886 | $610 | - | $25,942 332,256 kWh |
$(-811) (-177) kW-months/year |
$11,494 886 MMBtu |
$610 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Ancillary Material Cost |