Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2016 |
Principal Product | Recycled plastic pellets |
NAICS | 326199 - All Other Plastics Product Manufacturing |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 117,000 |
Annual Production | 72,000,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $811,838 | 19,452,000 | kWh | $0.04 |
Electricity Demand | $345,513 | 30,951 | kW-months/year | $11.16 |
Electricity Fees | $(-75,117) | - | $ | - |
Natural Gas | $69,117 | 8,682 | MMBtu | $7.96 |
TOTAL ENERGY COSTS | $1,151,351 | |||
RECOMMENDED SAVINGS* | $137,115 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $46,324 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $84,927 Cost: $200 |
$84,927 | - | - | - | - | - | - | - |
$84,927 - kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $30,556 Cost: $36,876 |
$19,302 | 462,874 | $7,379 | 661 | - | - | $3,875 | - |
$19,302 462,874 kWh |
$7,379 661 kW-months/year |
- - $ |
$3,875 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $8,668 Cost: $27,490 |
$4,505 | 108,037 | $2,510 | 225 | - | - | $1,653 | - |
$4,505 108,037 kWh |
$2,510 225 kW-months/year |
- - $ |
$1,653 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $910 Cost: $2,559 |
$480 | 11,519 | - | - | - | - | $430 | - |
$480 11,519 kWh |
- - kW-months/year |
- - $ |
$430 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $425 Cost: $1,071 |
$425 | 10,196 | - | - | - | - | - | - |
$425 10,196 kWh |
- - kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $3,735 Cost: $300 |
$3,266 | 78,330 | $1,249 | 112 | $(-300) | - | $(-480) | - |
$3,266 78,330 kWh |
$1,249 112 kW-months/year |
$(-300) - $ |
$(-480) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $2,696 Cost: $100 |
$1,950 | 46,768 | $746 | 67 | - | - | - | - |
$1,950 46,768 kWh |
$746 67 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4151 DEVELOP A REPAIR/REPLACE POLICY |
Savings: $3,168 Cost: $5,865 |
$2,292 | 54,960 | $876 | 78 | - | - | - | - |
$2,292 54,960 kWh |
$876 78 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,030 Cost: $230 |
$1,469 | 35,216 | $561 | 50 | - | - | - | - |
$1,469 35,216 kWh |
$561 50 kW-months/year |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $137,115 Cost: $74,691 |
$118,616 | 807,900 | $13,321 | 1,193 | $(-300) | - | $5,478 | - | $118,616 807,900 kWh |
$13,321 1,193 kW-months/year |
$(-300) - $ |
$5,478 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $46,324 Cost: $68,526 |
$29,447 | 706,172 | $11,699 | 1,048 | $(-300) | - | $5,478 | - | $29,447 706,172 kWh |
$11,699 1,048 kW-months/year |
$(-300) - $ |
$5,478 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Personnel Changes | Ancillary Material Cost |