IAC Assessment: NC0581
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0581
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2016
Principal Product Corrugated boxes
NAICS 322211 - Corrugated and Solid Fiber Box Manufacturing
SIC 2653 - Corrugated And Solid Fiber Boxes
Sales $10,000,000-$50,000,000
# of Employees 158
Plant Area (Sq.Ft.) 190,000
Annual Production 216,000 Thousand Feet
Production Hrs. Annual 6,000
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $187,919 4,616,616 kWh $0.04
Electricity Demand $119,221 10,297 kW-months/year $11.58
Electricity Fees $1,700 - $ -
Natural Gas $224,625 47,290 MMBtu $4.75
TOTAL ENERGY COSTS $534,345
RECOMMENDED SAVINGS* $53,187 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $15,141
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $ $ $
01: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$20,175
Cost:
$500
$20,175 - - - - - - - - - - - $20,175
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$14,986
Cost:
$45,747
$7,441 182,817 $4,990 431 - - - - - - $2,555 - $7,441
182,817
kWh
$4,990
431
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
$2,555
-
$
03: 2.7134 USE PHOTOCELL CONTROLS Savings:
$1,319
Cost:
$1,000
$1,319 32,400 - - - - - - - - - - $1,319
32,400
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$155
Cost:
$200
$596 14,637 $339 29 - - - - $(-300) - $(-480) - $596
14,637
kWh
$339
29
kW-months/year
-
-
MMBtu
-
-
gal
$(-300)
-
$
$(-480)
-
$
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,139
Cost:
$3,000
$2,637 64,800 $1,502 130 - - - - - - - - $2,637
64,800
kWh
$1,502
130
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
06: 2.7313 RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING Savings:
$8,569
Cost:
$25,000
- - - - $8,569 1,804 - - - - - - -
-
kWh
-
-
kW-months/year
$8,569
1,804
MMBtu
-
-
gal
-
-
$
-
-
$
07: 3.6124 BURN WASTE OIL FOR HEAT Savings:
$1,336
Cost:
$5,400
- - - - $456 96 $880 844 - - - - -
-
kWh
-
-
kW-months/year
$456
96
MMBtu
$880
844
gal
-
-
$
-
-
$
08: 2.4151 DEVELOP A REPAIR/REPLACE POLICY Savings:
$2,508
Cost:
$5,865
$1,598 39,257 $910 78 - - - - - - - - $1,598
39,257
kWh
$910
78
kW-months/year
-
-
MMBtu
-
-
gal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$53,187
Cost:
$86,712
$33,766 333,911 $7,741 668 $9,025 1,900 $880 844 $(-300) - $2,075 - $33,766
333,911
kWh
$7,741
668
kW-months/year
$9,025
1,900
MMBtu
$880
844
gal
$(-300)
-
$
$2,075
-
$
TOTAL IMPLEMENTED Savings:
$15,141
Cost:
$45,947
$8,037 197,454 $5,329 460 - - - - $(-300) - $2,075 - $8,037
197,454
kWh
$5,329
460
kW-months/year
-
-
MMBtu
-
-
gal
$(-300)
-
$
$2,075
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ $ $ $
Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Other Liquid (non-haz) Personnel Changes Ancillary Material Cost