IAC Assessment: NC0593
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0593
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2017
Principal Product High speed packaging machines
NAICS 333993 - Packaging Machinery Manufacturing
SIC 3565 - Packaging Machinery
Sales $10,000,000-$50,000,000
# of Employees 70
Plant Area (Sq.Ft.) 87,000
Annual Production 3 Pieces
Production Hrs. Annual 2,625
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $97,289 1,628,588 kWh $0.06
Electricity Demand $20,117 4,859 kW-months/year $4.14
Natural Gas $12,983 1,584 MMBtu $8.20
TOTAL ENERGY COSTS $130,837
RECOMMENDED SAVINGS* $23,648 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $23,529
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Electricity Usage Electricity Demand Natural Gas Other Liquid (haz)
$ kWh $ kW-months/year $ MMBtu $ gal
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$17,891
Cost:
$81,460
$13,744 230,219 $4,147 928 - - - - $13,744
230,219
kWh
$4,147
928
kW-months/year
-
-
MMBtu
-
-
gal
02: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$2,060
Cost:
$1,000
$1,568 26,271 $492 110 - - - - $1,568
26,271
kWh
$492
110
kW-months/year
-
-
MMBtu
-
-
gal
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$941
Cost:
$1,500
$941 15,765 - - - - - - $941
15,765
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
04: 2.7134 USE PHOTOCELL CONTROLS Savings:
$223
Cost:
$100
$223 3,739 - - - - - - $223
3,739
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$428
Cost:
$100
$319 5,342 $109 24 - - - - $319
5,342
kWh
$109
24
kW-months/year
-
-
MMBtu
-
-
gal
06: 3.3125 USE DISTILLATION, EVAPORATION TO REMOVE CONTAMINANTS Savings:
$119
Cost:
$300
$(-78) (-1,312) $(-27) (-6) - - $224 224 $(-78)
(-1,312)
kWh
$(-27)
(-6)
kW-months/year
-
-
MMBtu
$224
224
gal
07: 2.7442 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE Savings:
$1,986
Cost:
$600
$174 2,917 - - $1,812 221 - - $174
2,917
kWh
-
-
kW-months/year
$1,812
221
MMBtu
-
-
gal
TOTAL RECOMMENDED Savings:
$23,648
Cost:
$85,060
$16,891 282,941 $4,721 1,056 $1,812 221 $224 224 $16,891
282,941
kWh
$4,721
1,056
kW-months/year
$1,812
221
MMBtu
$224
224
gal
TOTAL IMPLEMENTED Savings:
$23,529
Cost:
$84,760
$16,969 284,253 $4,748 1,062 $1,812 221 - - $16,969
284,253
kWh
$4,748
1,062
kW-months/year
$1,812
221
MMBtu
-
-
gal
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Electricity Usage Electricity Demand Natural Gas Other Liquid (haz)