IAC Assessment: NC0612
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NC0612
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center North Carolina State
Assessment Year 2018
Principal Product Exhaust system parts
NAICS 336390 - Other Motor Vehicle Parts Manufacturing
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $100,000,000-$500,000,000
# of Employees 300
Plant Area (Sq.Ft.) 630,000
Annual Production 2,500,000 Pieces
Production Hrs. Annual 2,500
Location (State) NC
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $409,571 6,428,000 kWh $0.06
Electricity Demand $130,352 23,345 kW-months/year $5.58
TOTAL ENERGY COSTS $539,923
RECOMMENDED SAVINGS* $101,708 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $59,348
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,709
Cost:
$16,988
$3,040 47,947 $669 105 - - - - $3,040
47,947
kWh
$669
105
kW-months/year
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$36,235
Cost:
$215,800
$30,345 478,621 $5,890 920 - - - - $30,345
478,621
kWh
$5,890
920
kW-months/year
-
-
$
-
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$467
Cost:
$150
$467 7,371 - - - - - - $467
7,371
kWh
-
-
kW-months/year
-
-
$
-
-
$
04: 2.7124 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED Savings:
$14,909
Cost:
$500
$14,909 235,152 - - - - - - $14,909
235,152
kWh
-
-
kW-months/year
-
-
$
-
-
$
05: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,028
Cost:
$200
$3,252 51,300 $1,576 246 $(-400) - $(-400) - $3,252
51,300
kWh
$1,576
246
kW-months/year
$(-400)
-
$
$(-400)
-
$
06: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$42,360
Cost:
$500
$42,360 - - - - - - - $42,360
-
kWh
-
-
kW-months/year
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$101,708
Cost:
$234,138
$94,373 820,391 $8,135 1,271 $(-400) - $(-400) - $94,373
820,391
kWh
$8,135
1,271
kW-months/year
$(-400)
-
$
$(-400)
-
$
TOTAL IMPLEMENTED Savings:
$59,348
Cost:
$233,638
$52,013 820,391 $8,135 1,271 $(-400) - $(-400) - $52,013
820,391
kWh
$8,135
1,271
kW-months/year
$(-400)
-
$
$(-400)
-
$
Savings
Cost
$ kWh $ kW-months/year $ $ $ $
Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Personnel Changes Ancillary Material Cost