Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | North Carolina State |
---|---|
Assessment Year | 2018 |
Principal Product | Fabrics |
NAICS | 336360 - Motor Vehicle Seating and Interior Trim Manufacturing |
SIC | 2396 - Automotive And Apparel Trimmings |
Sales | $10,000,000-$50,000,000 |
# of Employees | 125 |
Plant Area (Sq.Ft.) | 300,000 |
Annual Production | 11,000 Thousand Feet |
Production Hrs. Annual | 6,000 |
Location (State) | NC |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $627,886 | 11,941,445 | kWh | $0.05 |
Electricity Demand | $223,086 | 22,601 | kW-months/year | $9.87 |
Natural Gas | $717,426 | 158,263 | MMBtu | $4.53 |
TOTAL ENERGY COSTS | $1,568,398 | |||
RECOMMENDED SAVINGS* | $66,371 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,921 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,801 Cost: $500 |
$2,529 | 45,160 | $776 | 90 | - | - | - | - | $(-480) | - | $(-24) | - |
$2,529 45,160 kWh |
$776 90 kW-months/year |
- - MMBtu |
- - Tgal |
$(-480) - $ |
$(-24) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4239 ELIMINATE OR REDUCE COMPRESSED AIR USAGE |
Savings: $1,322 Cost: $900 |
$1,322 | 23,615 | - | - | - | - | - | - | - | - | - | - |
$1,322 23,615 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $2,320 Cost: $1,203 |
- | - | - | - | $2,320 | 512 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,320 512 MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS |
Savings: $6,478 Cost: $16,800 |
$(-580) | (-10,350) | $(-422) | (-49) | - | - | $32,480 | 16,000 | $(-25,000) | - | - | - |
$(-580) (-10,350) kWh |
$(-422) (-49) kW-months/year |
- - MMBtu |
$32,480 16,000 Tgal |
$(-25,000) - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT |
Savings: $14,884 Cost: $10,000 |
$14,884 | 265,790 | - | - | - | - | - | - | - | - | - | - |
$14,884 265,790 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4154 AVOID REWINDING MOTORS MORE THAN TWICE |
Savings: $38,566 Cost: $70,014 |
$29,512 | 526,997 | $9,054 | 1,054 | - | - | - | - | - | - | - | - |
$29,512 526,997 kWh |
$9,054 1,054 kW-months/year |
- - MMBtu |
- - Tgal |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $66,371 Cost: $99,417 |
$47,667 | 851,212 | $9,408 | 1,095 | $2,320 | 512 | $32,480 | 16,000 | $(-25,480) | - | $(-24) | - | $47,667 851,212 kWh |
$9,408 1,095 kW-months/year |
$2,320 512 MMBtu |
$32,480 16,000 Tgal |
$(-25,480) - $ |
$(-24) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,921 Cost: $19,403 |
$3,271 | 58,425 | $354 | 41 | $2,320 | 512 | $32,480 | 16,000 | $(-25,480) | - | $(-24) | - | $3,271 58,425 kWh |
$354 41 kW-months/year |
$2,320 512 MMBtu |
$32,480 16,000 Tgal |
$(-25,480) - $ |
$(-24) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Personnel Changes | Ancillary Material Cost |