Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Notre Dame Univ. |
---|---|
Assessment Year | 1992 |
Principal Product | AUTOMOTIVE OEM PARTS |
NAICS | n/a |
SIC | 3714 - Motor Vehicle Parts And Accessories |
Sales | $5,000,000-$10,000,000 |
# of Employees | 86 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,400,000 Pieces |
Production Hrs. Annual | 6,240 |
Location (State) | OH |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $176,432 | 1,692,263 | kWh | $0.10 |
Fuel Oil #2 | $4,845 | 917 | MMBtu | $5.28 |
TOTAL ENERGY COSTS | $181,277 | |||
RECOMMENDED SAVINGS* | $10,862 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,626 |
#|Description |
Savings Cost |
Status | Electricity Usage | Fuel Oil #2 | Administrative Changes | Electricity Usage | Fuel Oil #2 | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,236 Cost: $1,550 |
$1,236 | 12,016 | - | - | - | - |
$1,236 12,016 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,082 Cost: $1,170 |
$5,608 | 55,393 | - | - | $(-526) | - |
$5,608 55,393 kWh |
- - MMBtu |
$(-526) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,160 Cost: $200 |
$4,160 | 39,859 | - | - | - | - |
$4,160 39,859 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $384 Cost: $400 |
- | - | $384 | 73 | - | - |
- - kWh |
$384 73 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $10,862 Cost: $3,320 |
$11,004 | 107,268 | $384 | 73 | $(-526) | - | $11,004 107,268 kWh |
$384 73 MMBtu |
$(-526) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,626 Cost: $1,770 |
$9,768 | 95,252 | $384 | 73 | $(-526) | - | $9,768 95,252 kWh |
$384 73 MMBtu |
$(-526) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Fuel Oil #2 | Administrative Changes | Electricity Usage | Fuel Oil #2 | Administrative Changes |