IAC logo
IAC Assessment: ND0020
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: ND0020
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Notre Dame Univ.
Assessment Year 1992
Principal Product ORIGINAL AUTO EQUIPMENT
NAICS n/a
SIC 3714 - Motor Vehicle Parts And Accessories
Sales $10,000,000-$50,000,000
# of Employees 56
Plant Area (Sq.Ft.) 0
Annual Production 1,100,000 Pieces
Production Hrs. Annual 6,240
Location (State) OH
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $134,024 1,324,150 kWh $0.10
Fuel Oil #2 $2,811 538 MMBtu $5.22
TOTAL ENERGY COSTS $136,835
RECOMMENDED SAVINGS* $15,146 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $8,535
#|Description Savings
Cost
Status Electricity Usage LPG Fuel Oil #2 Administrative Changes Electricity Usage LPG Fuel Oil #2 Administrative Changes
$ kWh $ MMBtu $ MMBtu $ $
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,557
Cost:
$1,707
$1,557 15,533 - - - - - - $1,557
15,533
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$8,080
Cost:
$400
$8,080 79,719 - - - - - - $8,080
79,719
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,675
Cost:
-
$2,945 29,015 - - - - $(-270) - $2,945
29,015
kWh
-
-
MMBtu
-
-
MMBtu
$(-270)
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,278
Cost:
$250
$2,278 22,567 - - - - - - $2,278
22,567
kWh
-
-
MMBtu
-
-
MMBtu
-
-
$
05: 2.7492 USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE Savings:
$232
Cost:
$300
- - - - $232 44 - - -
-
kWh
-
-
MMBtu
$232
44
MMBtu
-
-
$
06: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$223
Cost:
$400
- - - - $223 43 - - -
-
kWh
-
-
MMBtu
$223
43
MMBtu
-
-
$
07: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$101
Cost:
-
$164 1,758 $(-63) (-7) - - - - $164
1,758
kWh
$(-63)
(-7)
MMBtu
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$15,146
Cost:
$3,057
$15,024 148,592 $(-63) (-7) $455 87 $(-270) - $15,024
148,592
kWh
$(-63)
(-7)
MMBtu
$455
87
MMBtu
$(-270)
-
$
TOTAL IMPLEMENTED Savings:
$8,535
Cost:
$1,100
$8,080 79,719 - - $455 87 - - $8,080
79,719
kWh
-
-
MMBtu
$455
87
MMBtu
-
-
$
Savings
Cost
$ kWh $ MMBtu $ MMBtu $ $
Electricity Usage LPG Fuel Oil #2 Administrative Changes Electricity Usage LPG Fuel Oil #2 Administrative Changes