Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Notre Dame Univ. |
---|---|
Assessment Year | 1995 |
Principal Product | Hard Chrome Plated Rolls |
NAICS | n/a |
SIC | 3471 - Plating And Polishing |
Sales | $1,000,000-$5,000,000 |
# of Employees | 42 |
Plant Area (Sq.Ft.) | 45,000 |
Annual Production | 21,600 Pieces |
Production Hrs. Annual | 8,760 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $214,879 | 2,640,680 | kWh | $0.08 |
Natural Gas | $20,282 | 4,454 | MMBtu | $4.55 |
TOTAL ENERGY COSTS | $243,457 | |||
RECOMMENDED SAVINGS* | $40,178 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $37,106 |
#|Description |
Savings Cost |
Status | Electricity Usage | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | Electricity Usage | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | Tgal | $ | gal | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $2,453 Cost: $2,830 |
$2,453 | 30,188 | - | - | - | - | - | - |
$2,453 30,188 kWh |
- - Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2311 HEAT TREAT PARTS ONLY TO REQUIRED SPECIFICATIONS OR STANDARDS |
Savings: $1,082 Cost: $500 |
$1,082 | 13,189 | - | - | - | - | - | - |
$1,082 13,189 kWh |
- - Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $772 Cost: $150 |
$772 | 9,379 | - | - | - | - | - | - |
$772 9,379 kWh |
- - Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $619 Cost: $459 |
$619 | 7,620 | - | - | - | - | - | - |
$619 7,620 kWh |
- - Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $201 Cost: $250 |
$201 | 2,345 | - | - | - | - | - | - |
$201 2,345 kWh |
- - Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $101 Cost: - |
$101 | 1,172 | - | - | - | - | - | - |
$101 1,172 kWh |
- - Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4113 TREAT AND REUSE RINSE WATERS |
Savings: $27,000 Cost: $45,000 |
- | - | $27,000 | 240,000 | - | - | - | - |
- - kWh |
$27,000 240,000 Tgal |
- - gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE |
Savings: $7,300 Cost: $400 |
- | - | - | - | $7,300 | 2,800 | - | - |
- - kWh |
- - Tgal |
$7,300 2,800 gal |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.6111 USE ALTERNATIVE FLOCCULENT TO MINIMIZE SLUDGE VOLUME |
Savings: $650 Cost: $3,500 |
- | - | - | - | - | - | $650 | 3,420 |
- - kWh |
- - Tgal |
- - gal |
$650 3,420 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $40,178 Cost: $53,089 |
$5,228 | 63,893 | $27,000 | 240,000 | $7,300 | 2,800 | $650 | 3,420 | $5,228 63,893 kWh |
$27,000 240,000 Tgal |
$7,300 2,800 gal |
$650 3,420 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $37,106 Cost: $49,800 |
$2,156 | 26,085 | $27,000 | 240,000 | $7,300 | 2,800 | $650 | 3,420 | $2,156 26,085 kWh |
$27,000 240,000 Tgal |
$7,300 2,800 gal |
$650 3,420 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | Tgal | $ | gal | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) | Electricity Usage | Water Disposal | Other Liquid (non-haz) | Other Liquid (haz) |