Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Notre Dame Univ. |
---|---|
Assessment Year | 1996 |
Principal Product | Vacuum Formed Plastic |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 50 |
Plant Area (Sq.Ft.) | 60,000 |
Annual Production | 1,000,000 Pounds |
Production Hrs. Annual | 4,290 |
Location (State) | IN |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $101,648 | 1,345,252 | kWh | $0.08 |
Electricity Demand | $37,813 | 1,707 | kW-months/year | $22.15 |
Natural Gas | $9,653 | 2,445 | MMBtu | $3.95 |
TOTAL ENERGY COSTS | $150,339 | |||
RECOMMENDED SAVINGS* | $83,107 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $2,267 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,007 Cost: $80 |
$1,007 | 13,189 | - | - | - | - | - | - |
$1,007 13,189 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $914 Cost: $200 |
$914 | 12,016 | - | - | - | - | - | - |
$914 12,016 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $232 Cost: $360 |
$232 | 2,931 | - | - | - | - | - | - |
$232 2,931 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $386 Cost: $527 |
$242 | 3,224 | $144 | 6 | - | - | - | - |
$242 3,224 kWh |
$144 6 kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $109 Cost: $504 |
$109 | 2,345 | - | - | - | - | - | - |
$109 2,345 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $642 Cost: $3,360 |
$403 | 5,275 | $239 | 11 | - | - | - | - |
$403 5,275 kWh |
$239 11 kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $590 Cost: $1,400 |
$590 | 7,620 | - | - | - | - | - | - |
$590 7,620 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $76,364 Cost: $56,397 |
$92,309 | 1,201,348 | - | - | $(-15,945) | (-3,336) | - | - |
$92,309 1,201,348 kWh |
- - kW-months/year |
$(-15,945) (-3,336) MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $1,638 Cost: $80 |
$1,638 | 21,395 | - | - | - | - | - | - |
$1,638 21,395 kWh |
- - kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 3.2123 CONVERT TO HIGH VOLUME LOW PRESSURE (HVLP) PAINT GUNS |
Savings: $1,225 Cost: $200 |
- | - | - | - | - | - | $1,225 | 35 |
- - kWh |
- - kW-months/year |
- - MMBtu |
$1,225 35 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $83,107 Cost: $63,108 |
$97,444 | 1,269,343 | $383 | 17 | $(-15,945) | (-3,336) | $1,225 | 35 | $97,444 1,269,343 kWh |
$383 17 kW-months/year |
$(-15,945) (-3,336) MMBtu |
$1,225 35 gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $2,267 Cost: $4,327 |
$1,884 | 24,619 | $383 | 17 | - | - | - | - | $1,884 24,619 kWh |
$383 17 kW-months/year |
- - MMBtu |
- - gal |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | gal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) | Electricity Usage | Electricity Demand | Natural Gas | Other Liquid (non-haz) |