IAC Assessment: NL0023
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NL0023
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Nebraska–Lincoln
Assessment Year 2018
Principal Product Motor Fan Clutches
NAICS 336390 - Other Motor Vehicle Parts Manufacturing
SIC 3519 - Internal Combustion Engines, Nec
Sales $100,000,000-$500,000,000
# of Employees 180
Plant Area (Sq.Ft.) 155,000
Annual Production 250,000 Units
Production Hrs. Annual 5,980
Location (State) SD
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $331,584 6,960,000 kWh $0.05
Electricity Demand $131,403 17,071 kW-months/year $7.70
Electricity Fees $21,505 - $ -
LPG $34,971 2,363 MMBtu $14.80
TOTAL ENERGY COSTS $525,418
RECOMMENDED SAVINGS* $29,931 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $21,511
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Water Disposal Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Water Disposal Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ Tgal $ $ $ $
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$19,027
Cost:
$132,430
$13,410 279,381 $3,710 550 - - $1,907 - - - $13,410
279,381
kWh
$3,710
550
kW-months/year
-
-
Tgal
$1,907
-
$
-
-
$
02: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$8,100
Cost:
-
- - $8,100 1,200 - - - - - - -
-
kWh
$8,100
1,200
kW-months/year
-
-
Tgal
-
-
$
-
-
$
03: 3.5311 RECOVER AND REUSE WASTE MATERIAL Savings:
$2,484
Cost:
$7,000
- - - - - - - - $2,484 - -
-
kWh
-
-
kW-months/year
-
-
Tgal
-
-
$
$2,484
-
$
04: 3.4155 METER WASTE WATER Savings:
$320
Cost:
-
- - - - $320 97 - - - - -
-
kWh
-
-
kW-months/year
$320
97
Tgal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$29,931
Cost:
$139,430
$13,410 279,381 $11,810 1,750 $320 97 $1,907 - $2,484 - $13,410
279,381
kWh
$11,810
1,750
kW-months/year
$320
97
Tgal
$1,907
-
$
$2,484
-
$
TOTAL IMPLEMENTED Savings:
$21,511
Cost:
$139,430
$13,410 279,381 $3,710 550 - - $1,907 - $2,484 - $13,410
279,381
kWh
$3,710
550
kW-months/year
-
-
Tgal
$1,907
-
$
$2,484
-
$
Savings
Cost
$ kWh $ kW-months/year $ Tgal $ $ $ $
Electricity Usage Electricity Demand Water Disposal Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Water Disposal Personnel Changes Ancillary Material Cost