Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1996 |
Principal Product | Bottled Soft Drinks |
NAICS | n/a |
SIC | 2086 - Bottled And Canned Soft Drinks |
Sales | $10,000,000-$50,000,000 |
# of Employees | 190 |
Plant Area (Sq.Ft.) | 140,000 |
Annual Production | 6,000,000 Units |
Production Hrs. Annual | 4,680 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $184,283 | 3,155,627 | kWh | $0.06 |
Electricity Demand | $71,982 | 9,412 | kW-months/year | $7.65 |
Electricity Fees | $17,241 | - | $ | - |
Natural Gas | $18,411 | 3,460 | MMBtu | $5.32 |
TOTAL ENERGY COSTS | $292,430 | |||
RECOMMENDED SAVINGS* | $17,347 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $15,115 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $366 Cost: $100 |
$366 | 6,155 | - | - | - | - |
$366 6,155 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $823 Cost: $208 |
$573 | 9,965 | $250 | 33 | - | - |
$573 9,965 kWh |
$250 33 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $863 Cost: $163 |
$689 | 11,723 | $174 | 45 | - | - |
$689 11,723 kWh |
$174 45 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $10,850 Cost: $860 |
$5,197 | 89,097 | $5,653 | 739 | - | - |
$5,197 89,097 kWh |
$5,653 739 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $1,700 Cost: $2,000 |
$1,700 | 29,015 | - | - | - | - |
$1,700 29,015 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $630 Cost: $700 |
$630 | 10,844 | - | - | - | - |
$630 10,844 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $881 Cost: $310 |
$881 | 15,240 | - | - | - | - |
$881 15,240 kWh |
- - kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $721 Cost: $69 |
$554 | 25,791 | $167 | 66 | - | - |
$554 25,791 kWh |
$167 66 kW-months/year |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 3.4151 MINIMIZE WATER USAGE |
Savings: $513 Cost: - |
- | - | - | - | $513 | 442,320 |
- - kWh |
- - kW-months/year |
$513 442,320 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $17,347 Cost: $4,410 |
$10,590 | 197,830 | $6,244 | 883 | $513 | 442,320 | $10,590 197,830 kWh |
$6,244 883 kW-months/year |
$513 442,320 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $15,115 Cost: $3,331 |
$8,525 | 145,955 | $6,077 | 817 | $513 | 442,320 | $8,525 145,955 kWh |
$6,077 817 kW-months/year |
$513 442,320 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Electricity Usage | Electricity Demand | Water Disposal |