IAC Assessment: NV0081
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: NV0081
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center University of Nevada
Assessment Year 1997
Principal Product Steel Doors
NAICS n/a
SIC 3442 - Metal Doors, Sash, And Trim
Sales $100,000,000-$500,000,000
# of Employees 52
Plant Area (Sq.Ft.) 120,000
Annual Production 5,000 Thousand Feet
Production Hrs. Annual 3,320
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $75,951 1,121,336 kWh $0.07
Electricity Demand $28,424 3,651 kW-months/year $7.79
Electricity Fees $4,784 - $ -
Natural Gas $7,066 1,223 MMBtu $5.78
TOTAL ENERGY COSTS $116,225
RECOMMENDED SAVINGS* $130,624 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $75,254
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Primary Product Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Primary Product
$ kWh $ kW-months/year $ MMBtu $ lb $ $
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$3,967
Cost:
$170
$2,976 43,962 $991 127 - - - - - - $2,976
43,962
kWh
$991
127
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
02: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$2,948
Cost:
$1,330
- - - - $2,948 510 - - - - -
-
kWh
-
-
kW-months/year
$2,948
510
MMBtu
-
-
lb
-
-
$
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$2,173
Cost:
$1,500
- - - - $2,173 376 - - - - -
-
kWh
-
-
kW-months/year
$2,173
376
MMBtu
-
-
lb
-
-
$
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$872
Cost:
$360
$750 7,620 $122 16 - - - - - - $750
7,620
kWh
$122
16
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$435
Cost:
$32
$276 4,103 $159 20 - - - - - - $276
4,103
kWh
$159
20
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
06: 2.2515 USE OPTIMUM THICKNESS INSULATION Savings:
$2,717
Cost:
$11,160
- - - - $2,717 470 - - - - -
-
kWh
-
-
kW-months/year
$2,717
470
MMBtu
-
-
lb
-
-
$
07: 4.112 REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL Savings:
$1,164
Cost:
$2,120
$1,203 17,878 $(-39) (-5) - - - - - - $1,203
17,878
kWh
$(-39)
(-5)
kW-months/year
-
-
MMBtu
-
-
lb
-
-
$
08: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$30,328
Cost:
$155,000
- - - - - - - - $30,328 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$30,328
-
$
09: 4.122 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS Savings:
$60,656
Cost:
$12,000
- - - - - - - - $60,656 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$60,656
-
$
10: 4.111 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK Savings:
$15,164
Cost:
$20,000
- - - - - - - - $15,164 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
$15,164
-
$
11: 3.5315 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER Savings:
$8,160
Cost:
$20,000
- - - - - - $8,160 - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$8,160
-
lb
-
-
$
12: 4.221 USE ONLY AMOUNT OF PACKAGING MATERIAL NECESSARY Savings:
$2,040
Cost:
-
- - - - - - $2,040 1,013 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$2,040
1,013
lb
-
-
$
TOTAL RECOMMENDED Savings:
$130,624
Cost:
$223,672
$5,205 73,563 $1,233 158 $7,838 1,356 $10,200 1,013 $106,148 - $5,205
73,563
kWh
$1,233
158
kW-months/year
$7,838
1,356
MMBtu
$10,200
1,013
lb
$106,148
-
$
TOTAL IMPLEMENTED Savings:
$75,254
Cost:
$34,682
$5,205 73,563 $1,233 158 - - $8,160 - $60,656 - $5,205
73,563
kWh
$1,233
158
kW-months/year
-
-
MMBtu
$8,160
-
lb
$60,656
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb $ $
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Primary Product Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Primary Product