Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | University of Nevada |
---|---|
Assessment Year | 1998 |
Principal Product | Concrete Products |
NAICS | n/a |
SIC | 3272 - Concrete Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 68 |
Plant Area (Sq.Ft.) | 107,267 |
Annual Production | 709 Thousand Feet |
Production Hrs. Annual | 2,300 |
Location (State) | NV |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $23,036 | 541,325 | kWh | $0.04 |
Electricity Demand | $21,944 | 4,462 | kW-months/year | $4.92 |
Electricity Fees | $4,572 | - | $ | - |
Natural Gas | $34,037 | 6,568 | MMBtu | $5.18 |
TOTAL ENERGY COSTS | $84,260 | |||
RECOMMENDED SAVINGS* | $86,780 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $13,857 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $867 Cost: $2,852 |
$585 | 13,775 | $264 | 54 | $18 | - | - | - | - | - | - | - |
$585 13,775 kWh |
$264 54 kW-months/year |
$18 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,970 Cost: $9,180 |
$1,205 | 28,429 | $726 | 148 | $39 | - | - | - | - | - | - | - |
$1,205 28,429 kWh |
$726 148 kW-months/year |
$39 - $ |
- - MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.1224 REPLACE BOILER |
Savings: $12,990 Cost: $48,188 |
- | - | - | - | - | - | $12,990 | 2,520 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$12,990 2,520 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $746 Cost: $257 |
- | - | - | - | - | - | $746 | 145 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$746 145 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 4.821 PAY BILLS ON TIME TO AVOID LATE FEES |
Savings: $3,385 Cost: $750 |
- | - | - | - | - | - | - | - | - | - | $3,385 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
$3,385 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 4.652 REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES |
Savings: $60,255 Cost: $34,840 |
- | - | - | - | - | - | - | - | $60,255 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
$60,255 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 4.211 CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE |
Savings: $6,567 Cost: $1,500 |
- | - | - | - | - | - | - | - | - | - | $6,567 | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - $ |
$6,567 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $86,780 Cost: $97,567 |
$1,790 | 42,204 | $990 | 202 | $57 | - | $13,736 | 2,665 | $60,255 | - | $9,952 | - | $1,790 42,204 kWh |
$990 202 kW-months/year |
$57 - $ |
$13,736 2,665 MMBtu |
$60,255 - $ |
$9,952 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $13,857 Cost: $51,040 |
$585 | 13,775 | $264 | 54 | $18 | - | $12,990 | 2,520 | - | - | - | - | $585 13,775 kWh |
$264 54 kW-months/year |
$18 - $ |
$12,990 2,520 MMBtu |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Personnel Changes | Administrative Changes |