Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Old Dominion Univ. |
---|---|
Assessment Year | 1996 |
Principal Product | Prestressed Concrete Structures |
NAICS | n/a |
SIC | 3272 - Concrete Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 85 |
Plant Area (Sq.Ft.) | 100,000 |
Annual Production | 27,000 Pieces |
Production Hrs. Annual | 3,120 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $30,991 | 624,267 | kWh | $0.05 |
Electricity Demand | $8,150 | 1,691 | kW-months/year | $4.82 |
Electricity Fees | $353 | - | $ | - |
Natural Gas | $19,039 | 4,290 | MMBtu | $4.44 |
Fuel Oil #2 | $1,452 | 144 | MMBtu | $10.08 |
TOTAL ENERGY COSTS | $59,985 | |||
RECOMMENDED SAVINGS* | $111,262 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | By-product Production | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $1,986 Cost: $800 |
$1,986 | 45,428 | - | - | - | - | - | - | - | - | - | - | - | - |
$1,986 45,428 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $579 Cost: $20 |
$579 | 13,189 | - | - | - | - | - | - | - | - | - | - | - | - |
$579 13,189 kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,247 Cost: $1,602 |
$1,652 | 33,411 | $595 | 123 | - | - | - | - | - | - | - | - | - | - |
$1,652 33,411 kWh |
$595 123 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $239 Cost: $373 |
$151 | 2,931 | $88 | 18 | - | - | - | - | - | - | - | - | - | - |
$151 2,931 kWh |
$88 18 kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $879 Cost: $1,495 |
- | - | - | - | $879 | 198 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$879 198 MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $104,960 Cost: $2,400 |
- | - | - | - | - | - | - | 630,000 | $(-12,960) | - | $(-5,280) | - | $123,200 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- 630,000 lb |
$(-12,960) - $ |
$(-5,280) - $ |
$123,200 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5248 SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE |
Savings: $372 Cost: - |
- | - | - | - | - | - | $372 | 84,000 | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$372 84,000 lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $111,262 Cost: $6,690 |
$4,368 | 94,959 | $683 | 141 | $879 | 198 | $372 | 714,000 | $(-12,960) | - | $(-5,280) | - | $123,200 | - | $4,368 94,959 kWh |
$683 141 kW-months/year |
$879 198 MMBtu |
$372 714,000 lb |
$(-12,960) - $ |
$(-5,280) - $ |
$123,200 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | By-product Production | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | By-product Production |