Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Old Dominion Univ. |
---|---|
Assessment Year | 1996 |
Principal Product | Yarn and fabric |
NAICS | n/a |
SIC | 2211 - Broadwoven Fabric Mills, Cotton |
Sales | $50,000,000-$100,000,000 |
# of Employees | 432 |
Plant Area (Sq.Ft.) | 371,309 |
Annual Production | 70,750,000 Pounds |
Production Hrs. Annual | 8,400 |
Location (State) | VA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $712,534 | 43,926,144 | kWh | $0.02 |
Electricity Demand | $950,401 | 141,208 | kW-months/year | $6.73 |
Electricity Fees | $189,215 | - | $ | - |
Fuel Oil #6 | $1,861,104 | 504,756 | MMBtu | $3.69 |
TOTAL ENERGY COSTS | $3,713,254 | |||
RECOMMENDED SAVINGS* | $104,954 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $56,858 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Fuel Oil #6 | By-product Production | Electricity Usage | Electricity Demand | Fuel Oil #6 | By-product Production | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO |
Savings: $21,911 Cost: $1,400 |
- | - | - | - | $21,911 | 5,938 | - | - |
- - kWh |
- - kW-months/year |
$21,911 5,938 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $13,096 Cost: $5,800 |
- | - | - | - | $13,096 | 3,549 | - | - |
- - kWh |
- - kW-months/year |
$13,096 3,549 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $22,546 Cost: $51,404 |
$14,369 | 886,870 | $8,177 | 1,215 | - | - | - | - |
$14,369 886,870 kWh |
$8,177 1,215 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2612 USE COOLING TOWER WATER INSTEAD OF REFRIGERATION |
Savings: $4,186 Cost: $5,691 |
$2,833 | 144,783 | $1,353 | 201 | - | - | - | - |
$2,833 144,783 kWh |
$1,353 201 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $5,775 Cost: $19,955 |
$3,588 | 221,571 | $2,187 | 325 | - | - | - | - |
$3,588 221,571 kWh |
$2,187 325 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,440 Cost: $3,111 |
$1,531 | 94,666 | $909 | 135 | - | - | - | - |
$1,531 94,666 kWh |
$909 135 kW-months/year |
- - MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.5313 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE |
Savings: $35,000 Cost: - |
- | - | - | - | - | - | $35,000 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$35,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $104,954 Cost: $87,361 |
$22,321 | 1,347,890 | $12,626 | 1,876 | $35,007 | 9,487 | $35,000 | - | $22,321 1,347,890 kWh |
$12,626 1,876 kW-months/year |
$35,007 9,487 MMBtu |
$35,000 - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $56,858 Cost: $81,561 |
$22,321 | 1,347,890 | $12,626 | 1,876 | $21,911 | 5,938 | - | - | $22,321 1,347,890 kWh |
$12,626 1,876 kW-months/year |
$21,911 5,938 MMBtu |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Fuel Oil #6 | By-product Production | Electricity Usage | Electricity Demand | Fuel Oil #6 | By-product Production |