IAC Assessment: OD0111
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OD0111
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Old Dominion Univ.
Assessment Year 1998
Principal Product Concrete panels and structural members
NAICS n/a
SIC 3272 - Concrete Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 235
Plant Area (Sq.Ft.) 150,000
Annual Production 88,400 Units
Production Hrs. Annual 5,200
Location (State) VA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $42,697 2,435,229 kWh $0.02
Electricity Demand $135,916 9,598 kW-months/year $14.16
Electricity Fees $3,977 - $ -
Natural Gas $30,272 4,908 MMBtu $6.17
TOTAL ENERGY COSTS $217,393
RECOMMENDED SAVINGS* $16,322 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,322
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ gal $ lb
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,907
Cost:
$496
$547 31,360 $1,360 96 - - - - - - $547
31,360
kWh
$1,360
96
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$7,382
Cost:
$18,789
$3,163 181,125 $4,219 298 - - - - - - $3,163
181,125
kWh
$4,219
298
kW-months/year
-
-
MMBtu
-
-
gal
-
-
lb
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$2,962
Cost:
$200
- - - - $2,962 480 - - - - -
-
kWh
-
-
kW-months/year
$2,962
480
MMBtu
-
-
gal
-
-
lb
04: 3.8211 CONVERT TO AQUEOUS CLEANING SYSTEM Savings:
$1,029
Cost:
$1,300
- - - - - - $1,029 140 - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,029
140
gal
-
-
lb
05: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$3,042
Cost:
-
- - - - - - - - $3,042 1,000,000 -
-
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
gal
$3,042
1,000,000
lb
TOTAL RECOMMENDED Savings:
$16,322
Cost:
$20,785
$3,710 212,485 $5,579 394 $2,962 480 $1,029 140 $3,042 1,000,000 $3,710
212,485
kWh
$5,579
394
kW-months/year
$2,962
480
MMBtu
$1,029
140
gal
$3,042
1,000,000
lb
TOTAL IMPLEMENTED Savings:
$16,322
Cost:
$20,785
$3,710 212,485 $5,579 394 $2,962 480 $1,029 140 $3,042 1,000,000 $3,710
212,485
kWh
$5,579
394
kW-months/year
$2,962
480
MMBtu
$1,029
140
gal
$3,042
1,000,000
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ gal $ lb
Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Other Liquid (haz) Solid Waste (non-haz)