IAC Assessment: OK0025
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0025
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1982
Principal Product PLASTIC PIPE
NAICS n/a
SIC 3084 - Plastics Pipe
Sales $10,000,000-$50,000,000
# of Employees 400
Plant Area (Sq.Ft.) 0
Annual Production 80,000,000 Pounds
Production Hrs. Annual 8,736
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,241,577 21,470,106 kWh $0.06
Natural Gas $35,421 13,953 MMBtu $2.54
TOTAL ENERGY COSTS $1,276,998
RECOMMENDED SAVINGS* $25,680 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$173
Cost:
$293
$173 4,689 - - $173
4,689
kWh
-
-
MMBtu
02: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$14,183
Cost:
$18,620
$14,183 - - - $14,183
-
kWh
-
-
MMBtu
03: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$3,084
Cost:
$3,247
$3,084 123,388 - - $3,084
123,388
kWh
-
-
MMBtu
04: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$3,202
Cost:
$290
$3,202 147,421 - - $3,202
147,421
kWh
-
-
MMBtu
05: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$223
Cost:
$500
- - $223 84 -
-
kWh
$223
84
MMBtu
06: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$4,815
Cost:
$90,000
$5,897 95,545 $(-1,082) (-408) $5,897
95,545
kWh
$(-1,082)
(-408)
MMBtu
TOTAL RECOMMENDED Savings:
$25,680
Cost:
$112,950
$26,539 371,043 $(-859) (-324) $26,539
371,043
kWh
$(-859)
(-324)
MMBtu
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - -
-
kWh
-
-
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas