IAC logo
IAC Assessment: OK0154
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0154
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1985
Principal Product REFRIGERANTS
NAICS n/a
SIC 2813 - Industrial Gases
Sales $50,000,000-$100,000,000
# of Employees 45
Plant Area (Sq.Ft.) 0
Annual Production 48,000,000 Pounds
Production Hrs. Annual 8,736
Location (State) MO
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $672,927 15,669,989 kWh $0.04
Other Energy $635,005 141,486 MMBtu $4.49
TOTAL ENERGY COSTS $1,307,932
RECOMMENDED SAVINGS* $989,099 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $987,048
#|Description Savings
Cost
Status Electricity Usage Other Energy Administrative Changes Electricity Usage Other Energy Administrative Changes
$ kWh $ MMBtu $ $
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER Savings:
$13,315
Cost:
$12,158
$(-85) (-2,052) $13,400 2,196 - - $(-85)
(-2,052)
kWh
$13,400
2,196
MMBtu
-
-
$
02: 2.7447 INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS Savings:
$1,917
Cost:
$500
- - $1,917 365 - - -
-
kWh
$1,917
365
MMBtu
-
-
$
03: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$850
Cost:
-
$850 13,482 - - - - $850
13,482
kWh
-
-
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,201
Cost:
$546
$1,201 19,050 - - - - $1,201
19,050
kWh
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$661
Cost:
$1,142
$614 15,826 - - $47 - $614
15,826
kWh
-
-
MMBtu
$47
-
$
06: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$1,402
Cost:
$410
$1,402 24,912 - - - - $1,402
24,912
kWh
-
-
MMBtu
-
-
$
07: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,382
Cost:
$891
$1,382 35,463 - - - - $1,382
35,463
kWh
-
-
MMBtu
-
-
$
08: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$4,324
Cost:
$171
$424 16,413 $3,900 714 - - $424
16,413
kWh
$3,900
714
MMBtu
-
-
$
09: 2.3411 REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT Savings:
$4,309
Cost:
$13,674
$7,218 206,917 $(-2,909) (-639) - - $7,218
206,917
kWh
$(-2,909)
(-639)
MMBtu
-
-
$
10: 2.3416 USE COMBINED CYCLE GAS TURBINE GENERATOR SETS WITH WASTE HEAT BOILERS CONNECTED TO TURBINE EXHAUST Savings:
$959,738
Cost:
$1,018,080
$408,620 14,886,577 $603,255 134,412 $(-52,137) - $408,620
14,886,577
kWh
$603,255
134,412
MMBtu
$(-52,137)
-
$
TOTAL RECOMMENDED Savings:
$989,099
Cost:
$1,047,572
$421,626 15,216,588 $619,563 137,048 $(-52,090) - $421,626
15,216,588
kWh
$619,563
137,048
MMBtu
$(-52,090)
-
$
TOTAL IMPLEMENTED Savings:
$987,048
Cost:
$1,047,026
$419,575 15,184,056 $619,563 137,048 $(-52,090) - $419,575
15,184,056
kWh
$619,563
137,048
MMBtu
$(-52,090)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Other Energy Administrative Changes Electricity Usage Other Energy Administrative Changes