Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1985 |
Principal Product | AUTO PARTS |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $10,000,000-$50,000,000 |
# of Employees | 225 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 50,000,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $441,337 | 10,800,117 | kWh | $0.04 |
Natural Gas | $214,869 | 43,663 | MMBtu | $4.92 |
TOTAL ENERGY COSTS | $656,206 | |||
RECOMMENDED SAVINGS* | $53,658 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $12,034 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $567 Cost: $161 |
$567 | 11,723 | - | - | - | - |
$567 11,723 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $5,639 Cost: $7,640 |
$5,639 | - | - | - | - | - |
$5,639 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $16,728 Cost: $14,629 |
$15,524 | 394,490 | - | - | $1,204 | - |
$15,524 394,490 kWh |
- - MMBtu |
$1,204 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.4115 RECOVER AND REUSE COOLING WATER |
Savings: $1,387 Cost: $500 |
$29 | 586 | - | - | $1,358 | - |
$29 586 kWh |
- - MMBtu |
$1,358 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7121 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT |
Savings: $2,307 Cost: $624 |
$2,307 | 50,996 | - | - | - | - |
$2,307 50,996 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $9,735 Cost: - |
$11,400 | - | - | - | $(-1,665) | - |
$11,400 - kWh |
- - MMBtu |
$(-1,665) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME |
Savings: $1,633 Cost: $531 |
$575 | 17,585 | $1,058 | 215 | - | - |
$575 17,585 kWh |
$1,058 215 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $300 Cost: $329 |
- | - | $300 | 61 | - | - |
- - kWh |
$300 61 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $1,230 Cost: $300 |
- | - | $1,230 | 250 | - | - |
- - kWh |
$1,230 250 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7221 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA |
Savings: $2,411 Cost: - |
- | - | $2,411 | 490 | - | - |
- - kWh |
$2,411 490 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $290 Cost: $880 |
- | - | $290 | 59 | - | - |
- - kWh |
$290 59 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7312 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE |
Savings: $11,431 Cost: - |
$3,800 | 116,354 | $7,631 | 1,551 | - | - |
$3,800 116,354 kWh |
$7,631 1,551 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $53,658 Cost: $25,594 |
$39,841 | 591,734 | $12,920 | 2,626 | $897 | - | $39,841 591,734 kWh |
$12,920 2,626 MMBtu |
$897 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $12,034 Cost: $9,644 |
$7,975 | 51,582 | $2,701 | 549 | $1,358 | - | $7,975 51,582 kWh |
$2,701 549 MMBtu |
$1,358 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |