Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1986 |
Principal Product | PUMPS & MOTORS |
NAICS | n/a |
SIC | 3561 - Pumps And Pumping Equipment |
Sales | $10,000,000-$50,000,000 |
# of Employees | 250 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,500 Pieces |
Production Hrs. Annual | 5,100 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $353,724 | 6,514,947 | kWh | $0.05 |
Natural Gas | $77,915 | 21,459 | MMBtu | $3.63 |
TOTAL ENERGY COSTS | $431,639 | |||
RECOMMENDED SAVINGS* | $23,397 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $21,312 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $1,989 Cost: $500 |
$1,989 | 43,669 | - | - | - | - |
$1,989 43,669 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2532 USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD |
Savings: $2,085 Cost: $214 |
$372 | 12,603 | $1,713 | 463 | - | - |
$372 12,603 kWh |
$1,713 463 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2424 USE HEAT IN FLUE GASES TO PREHEAT PRODUCTS OR MATERIALS |
Savings: $2,520 Cost: $3,000 |
- | - | $2,520 | 681 | - | - |
- - kWh |
$2,520 681 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $12,902 Cost: - |
$12,902 | - | - | - | - | - |
$12,902 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3191 USE DEMAND CONTROLLER OR LOAD SHEDDER |
Savings: $1,289 Cost: $1,200 |
$1,289 | - | - | - | - | - |
$1,289 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $582 Cost: - |
$682 | 22,860 | - | - | $(-100) | - |
$682 22,860 kWh |
- - MMBtu |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2223 ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF |
Savings: $2,030 Cost: $1,200 |
$2,030 | 41,325 | - | - | - | - |
$2,030 41,325 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $23,397 Cost: $6,114 |
$19,264 | 120,457 | $4,233 | 1,144 | $(-100) | - | $19,264 120,457 kWh |
$4,233 1,144 MMBtu |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $21,312 Cost: $5,900 |
$18,892 | 107,854 | $2,520 | 681 | $(-100) | - | $18,892 107,854 kWh |
$2,520 681 MMBtu |
$(-100) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |