IAC logo
IAC Assessment: OK0212
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0212
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 1986
Principal Product STEEL UTILITY POLES
NAICS n/a
SIC 3441 - Fabricated Structural Metal
Sales $10,000,000-$50,000,000
# of Employees 135
Plant Area (Sq.Ft.) 0
Annual Production 0 Units
Production Hrs. Annual 4,420
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $125,541 2,153,869 kWh $0.06
Natural Gas $52,483 13,632 MMBtu $3.85
TOTAL ENERGY COSTS $178,024
RECOMMENDED SAVINGS* $23,946 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $23,946
#|Description Savings
Cost
Status Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes
$ kWh $ MMBtu $ $
01: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$1,745
Cost:
$485
- - $1,745 430 - - -
-
kWh
$1,745
430
MMBtu
-
-
$
02: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$4,403
Cost:
-
$4,843 109,027 - - $(-440) - $4,843
109,027
kWh
-
-
MMBtu
$(-440)
-
$
03: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS Savings:
$378
Cost:
$450
- - $378 93 - - -
-
kWh
$378
93
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,372
Cost:
$212
$1,372 28,136 - - - - $1,372
28,136
kWh
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$11,167
Cost:
$1,575
$11,167 157,386 - - - - $11,167
157,386
kWh
-
-
MMBtu
-
-
$
06: 2.6232 INSTALL SET-BACK TIMERS Savings:
$1,748
Cost:
-
$1,748 29,015 - - - - $1,748
29,015
kWh
-
-
MMBtu
-
-
$
07: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$3,133
Cost:
-
$3,702 - - - $(-569) - $3,702
-
kWh
-
-
MMBtu
$(-569)
-
$
TOTAL RECOMMENDED Savings:
$23,946
Cost:
$2,722
$22,832 323,564 $2,123 523 $(-1,009) - $22,832
323,564
kWh
$2,123
523
MMBtu
$(-1,009)
-
$
TOTAL IMPLEMENTED Savings:
$23,946
Cost:
$2,722
$22,832 323,564 $2,123 523 $(-1,009) - $22,832
323,564
kWh
$2,123
523
MMBtu
$(-1,009)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Administrative Changes Electricity Usage Natural Gas Administrative Changes