Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1989 |
Principal Product | CUSTOM BUSINESS FORMS |
NAICS | n/a |
SIC | 2761 - Manifold Business Forms |
Sales | $10,000,000-$50,000,000 |
# of Employees | 118 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 1,300,000 Pounds |
Production Hrs. Annual | 6,240 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $129,134 | 3,082,943 | kWh | $0.04 |
TOTAL ENERGY COSTS | $129,134 | |||
RECOMMENDED SAVINGS* | $34,431 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $14,383 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,071 Cost: $616 |
$2,071 | 42,790 | - | - | - | - |
$2,071 42,790 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $6,240 Cost: $15,500 |
$10,505 | 303,048 | $(-4,265) | (-1,292) | - | - |
$10,505 303,048 kWh |
$(-4,265) (-1,292) MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $505 Cost: $622 |
$568 | 9,965 | - | - | $(-63) | - |
$568 9,965 kWh |
- - MMBtu |
$(-63) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $1,924 Cost: $1,809 |
$1,924 | 43,962 | - | - | - | - |
$1,924 43,962 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS |
Savings: $2,638 Cost: - |
$2,638 | 60,668 | - | - | - | - |
$2,638 60,668 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $894 Cost: $215 |
$894 | 25,791 | - | - | - | - |
$894 25,791 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $616 Cost: - |
$646 | 18,757 | - | - | $(-30) | - |
$646 18,757 kWh |
- - MMBtu |
$(-30) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3511 USE PLANT OWNED TRANSFORMERS OR LEASE TRANSFORMERS |
Savings: $9,879 Cost: $15,700 |
$9,879 | - | - | - | - | - |
$9,879 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $9,664 Cost: $23,469 |
$9,664 | 278,722 | - | - | - | - |
$9,664 278,722 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $34,431 Cost: $57,931 |
$38,789 | 783,703 | $(-4,265) | (-1,292) | $(-93) | - | $38,789 783,703 kWh |
$(-4,265) (-1,292) MMBtu |
$(-93) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $14,383 Cost: $18,140 |
$18,678 | 495,016 | $(-4,265) | (-1,292) | $(-30) | - | $18,678 495,016 kWh |
$(-4,265) (-1,292) MMBtu |
$(-30) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |