Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 1998 |
Principal Product | Food-service products |
NAICS | n/a |
SIC | 3089 - Plastics Products, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 400 |
Plant Area (Sq.Ft.) | 165,000 |
Annual Production | 10,000,000 Pounds |
Production Hrs. Annual | 8,568 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $395,183 | 14,081,184 | kWh | $0.03 |
Electricity Demand | $257,605 | - | kW-months/year | - |
Electricity Fees | $(-44,479) | - | $ | - |
Natural Gas | $5,173 | 971 | MMBtu | $5.33 |
TOTAL ENERGY COSTS | $645,926 | |||
RECOMMENDED SAVINGS* | $251,370 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $227,268 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.5194 REDESIGN PROCESS |
Savings: $178,358 Cost: $248,000 |
- | - | - | - | - | - | $178,358 | - | - | - |
- - kWh |
- - kW-months/year |
- - lb |
$178,358 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $2,417 Cost: $39,746 |
$2,417 | 149,619 | - | - | - | - | - | - | - | - |
$2,417 149,619 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE |
Savings: $20,281 Cost: - |
- | - | - | - | - | - | - | - | $20,281 | - |
- - kWh |
- - kW-months/year |
- - lb |
- - $ |
$20,281 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $9,562 Cost: $9,700 |
- | - | - | - | $9,562 | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$9,562 - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $6,911 Cost: $5,543 |
- | - | $6,911 | 1,164 | - | - | - | - | - | - |
- - kWh |
$6,911 1,164 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $6,825 Cost: - |
$4,594 | 172,626 | $2,231 | 242 | - | - | - | - | - | - |
$4,594 172,626 kWh |
$2,231 242 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $6,214 Cost: $1,483 |
- | - | $6,214 | - | - | - | - | - | - | - |
- - kWh |
$6,214 - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7252 UTILIZE AN EVAPORATIVE AIR PRE-COOLER OR OTHER HEAT EXCHANGER IN AC SYSTEM |
Savings: $5,557 Cost: $25,000 |
$5,557 | 208,968 | - | - | - | - | - | - | - | - |
$5,557 208,968 kWh |
- - kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $5,002 Cost: $320 |
$3,367 | 126,612 | $1,635 | 177 | - | - | - | - | - | - |
$3,367 126,612 kWh |
$1,635 177 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $4,823 Cost: $2,100 |
$3,112 | 116,940 | $1,711 | 186 | - | - | - | - | - | - |
$3,112 116,940 kWh |
$1,711 186 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $2,573 Cost: $5,000 |
$1,732 | 65,064 | $841 | 91 | - | - | - | - | - | - |
$1,732 65,064 kWh |
$841 91 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,948 Cost: $1,080 |
$1,319 | 48,652 | $629 | 67 | - | - | - | - | - | - |
$1,319 48,652 kWh |
$629 67 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $899 Cost: $585 |
$609 | 34,584 | $290 | 31 | - | - | - | - | - | - |
$609 34,584 kWh |
$290 31 kW-months/year |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $251,370 Cost: $338,557 |
$22,707 | 923,065 | $20,462 | 1,958 | $9,562 | - | $178,358 | - | $20,281 | - | $22,707 923,065 kWh |
$20,462 1,958 kW-months/year |
$9,562 - lb |
$178,358 - $ |
$20,281 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $227,268 Cost: $299,866 |
$13,490 | 565,797 | $5,577 | 605 | $9,562 | - | $178,358 | - | $20,281 | - | $13,490 565,797 kWh |
$5,577 605 kW-months/year |
$9,562 - lb |
$178,358 - $ |
$20,281 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes | Electricity Usage | Electricity Demand | Solid Waste (non-haz) | Personnel Changes | Administrative Changes |