Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2003 |
Principal Product | Thrust Reversers, Nacelles |
NAICS | 336413 - Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728 - Aircraft Parts And Equipment, Nec |
Sales | $50,000,000-$100,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 375,000 |
Annual Production | 216 Pieces |
Production Hrs. Annual | 4,160 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $299,579 | 12,065,200 | kWh | $0.02 |
Electricity Demand | $169,901 | 39,975 | kW-months/year | $4.25 |
Electricity Fees | $44,104 | - | $ | - |
Natural Gas | $65,945 | 11,105 | MMBtu | $5.94 |
TOTAL ENERGY COSTS | $579,529 | |||
RECOMMENDED SAVINGS* | $65,272 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $19,851 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $5,885 Cost: $6,844 |
- | - | $5,885 | 960 | - | - | - | - | - | - |
- - kWh |
$5,885 960 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $28,340 Cost: - |
- | - | $28,340 | 6,668 | - | - | - | - | - | - |
- - kWh |
$28,340 6,668 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.8121 APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES |
Savings: $12,626 Cost: $2,000 |
- | - | - | - | - | - | $12,626 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$12,626 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS |
Savings: $2,333 Cost: $145 |
$1,362 | 54,912 | $971 | 158 | - | - | - | - | - | - |
$1,362 54,912 kWh |
$971 158 kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $1,041 Cost: - |
$1,041 | 41,933 | - | - | - | - | - | - | - | - |
$1,041 41,933 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $1,292 Cost: $8,190 |
- | - | - | - | - | - | $1,292 | - | - | - |
- - kWh |
- - kW-months/year |
- - Tgal |
$1,292 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) |
Savings: $7,225 Cost: $262 |
- | - | - | - | $7,225 | 2,500 | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,225 2,500 Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,952 Cost: $28,902 |
$3,719 | 149,760 | $2,648 | 432 | - | - | - | - | $(-415) | - |
$3,719 149,760 kWh |
$2,648 432 kW-months/year |
- - Tgal |
- - $ |
$(-415) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $578 Cost: $488 |
$578 | 23,296 | - | - | - | - | - | - | - | - |
$578 23,296 kWh |
- - kW-months/year |
- - Tgal |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $65,272 Cost: $46,831 |
$6,700 | 269,901 | $37,844 | 8,218 | $7,225 | 2,500 | $13,918 | - | $(-415) | - | $6,700 269,901 kWh |
$37,844 8,218 kW-months/year |
$7,225 2,500 Tgal |
$13,918 - $ |
$(-415) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $19,851 Cost: $2,262 |
- | - | - | - | $7,225 | 2,500 | $12,626 | - | - | - | - - kWh |
- - kW-months/year |
$7,225 2,500 Tgal |
$12,626 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | Tgal | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Water Disposal | Administrative Changes | Ancillary Material Cost |