IAC Assessment: OK0686
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0686
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2004
Principal Product Sucker Rods
NAICS 332996 - Fabricated Pipe and Pipe Fitting Manufacturing
SIC 3498 - Fabricated Pipe And Fittings
Sales $50,000,000-$100,000,000
# of Employees 200
Plant Area (Sq.Ft.) 230,000
Annual Production 35,000,000 Pieces
Production Hrs. Annual 6,240
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $568,031 12,383,440 kWh $0.05
Electricity Demand $1,689 5,630 kW-months/year $0.30
Electricity Fees $169,163 - $ -
Natural Gas $1,279,845 218,484 MMBtu $5.86
TOTAL ENERGY COSTS $2,036,728
RECOMMENDED SAVINGS* $111,908 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $16,089
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Personnel Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ $ $ $
01: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS Savings:
$13,360
Cost:
$160
- - $20,848 4,800 - - - - - - $(-7,488) - - - -
-
kWh
$20,848
4,800
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
$(-7,488)
-
$
-
-
$
02: 3.4116 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) Savings:
$1,472
Cost:
$262
- - - - - - $1,472 518,000 - - - - - - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$1,472
518,000
Tgal
-
-
gal
-
-
$
-
-
$
03: 2.7135 INSTALL OCCUPANCY SENSORS Savings:
$3,350
Cost:
$1,136
$3,350 105,357 - - - - - - - - - - - - $3,350
105,357
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
$
-
-
$
04: 2.6232 INSTALL SET-BACK TIMERS Savings:
$1,577
Cost:
$1,320
- - - - $1,577 269 - - - - - - - - -
-
kWh
-
-
kW-months/year
$1,577
269
MMBtu
-
-
Tgal
-
-
gal
-
-
$
-
-
$
05: 3.5146 UTILIZE A CENTRAL COOLANT SYSTEM FOR CLEANING AND REUSE OF METAL WORKING FLUID Savings:
$70,533
Cost:
$81,950
$(-713) (-18,720) - - - - - - $16,740 55,800 $(-5,200) - $59,706 - $(-713)
(-18,720)
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
Tgal
$16,740
55,800
gal
$(-5,200)
-
$
$59,706
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,153
Cost:
$36,618
$10,110 317,928 $1,827 421 - - - - - - - - $(-2,784) - $10,110
317,928
kWh
$1,827
421
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
$
$(-2,784)
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$537
Cost:
$2,550
$142 4,468 $27 6 - - - - - - - - $368 - $142
4,468
kWh
$27
6
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
$
$368
-
$
08: 2.2515 USE OPTIMUM THICKNESS INSULATION Savings:
$8,220
Cost:
$40,318
- - - - $8,220 1,403 - - - - - - - - -
-
kWh
-
-
kW-months/year
$8,220
1,403
MMBtu
-
-
Tgal
-
-
gal
-
-
$
-
-
$
09: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$3,706
Cost:
$22,116
$2,664 83,762 $1,042 240 - - - - - - - - - - $2,664
83,762
kWh
$1,042
240
kW-months/year
-
-
MMBtu
-
-
Tgal
-
-
gal
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$111,908
Cost:
$186,430
$15,553 492,795 $23,744 5,467 $9,797 1,672 $1,472 518,000 $16,740 55,800 $(-12,688) - $57,290 - $15,553
492,795
kWh
$23,744
5,467
kW-months/year
$9,797
1,672
MMBtu
$1,472
518,000
Tgal
$16,740
55,800
gal
$(-12,688)
-
$
$57,290
-
$
TOTAL IMPLEMENTED Savings:
$16,089
Cost:
$41,886
$13,602 427,753 $1,854 427 $1,577 269 $1,472 518,000 - - - - $(-2,416) - $13,602
427,753
kWh
$1,854
427
kW-months/year
$1,577
269
MMBtu
$1,472
518,000
Tgal
-
-
gal
-
-
$
$(-2,416)
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ Tgal $ gal $ $ $ $
Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Personnel Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Water Disposal Other Liquid (non-haz) Personnel Changes Ancillary Material Cost