Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2009 |
Principal Product | Powdered Metal Parts |
NAICS | 332117 - Powder Metallurgy Part Manufacturing |
SIC | 3499 - Fabricated Metal Products, Nec |
Sales | $5,000,000-$10,000,000 |
# of Employees | 71 |
Plant Area (Sq.Ft.) | 65,000 |
Annual Production | 8,000,000 Pounds |
Production Hrs. Annual | 7,488 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $306,828 | 5,317,840 | kWh | $0.06 |
Electricity Demand | $87,895 | 10,644 | kW-months/year | $8.26 |
Natural Gas | $23,549 | 1,984 | MMBtu | $11.87 |
TOTAL ENERGY COSTS | $418,272 | |||
RECOMMENDED SAVINGS* | $77,815 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,248 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $4,182 Cost: - |
$4,182 | 72,600 | - | - | - | - |
$4,182 72,600 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS |
Savings: $2,161 Cost: $2,326 |
$2,161 | 37,515 | - | - | - | - |
$2,161 37,515 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT |
Savings: $6,617 Cost: $5,534 |
- | - | - | - | $6,617 | 558 |
- - kWh |
- - kW-months/year |
$6,617 558 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,208 Cost: $11,677 |
$1,208 | 18,018 | - | - | - | - |
$1,208 18,018 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,179 Cost: $9,264 |
$2,179 | 40,361 | - | - | - | - |
$2,179 40,361 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $1,586 Cost: $4,119 |
$1,586 | 35,718 | - | - | - | - |
$1,586 35,718 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1121 USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING |
Savings: $5,419 Cost: $386 |
$5,419 | 94,080 | - | - | - | - |
$5,419 94,080 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.3137 USE POWER DURING OFF-PEAK PERIODS |
Savings: $30,940 Cost: - |
- | - | $30,940 | 3,250 | - | - |
- - kWh |
$30,940 3,250 kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.3417 USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT |
Savings: $19,665 Cost: $140,000 |
$19,665 | 336,960 | - | - | - | - |
$19,665 336,960 kWh |
- - kW-months/year |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $3,858 Cost: $2,925 |
- | - | - | - | $3,858 | 325 |
- - kWh |
- - kW-months/year |
$3,858 325 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $77,815 Cost: $176,231 |
$36,400 | 635,252 | $30,940 | 3,250 | $10,475 | 883 | $36,400 635,252 kWh |
$30,940 3,250 kW-months/year |
$10,475 883 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,248 Cost: $14,602 |
$5,390 | 90,618 | - | - | $3,858 | 325 | $5,390 90,618 kWh |
- - kW-months/year |
$3,858 325 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Electricity Usage | Electricity Demand | Natural Gas |