IAC Assessment: OK0813
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0813
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2011
Principal Product Oil country tubular goods
NAICS 331210 - Iron and Steel Pipe and Tube Manufacturing from Purchased Steel
SIC 3317 - Steel Pipe And Tubes
Sales $100,000,000-$500,000,000
# of Employees 170
Plant Area (Sq.Ft.) 3,284,424
Annual Production 65,000 Tons
Production Hrs. Annual 3,120
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $708,660 9,881,400 kWh $0.07
Electricity Demand $199,902 30,993 kW-months/year $6.45
Natural Gas $1,008,778 206,716 MMBtu $4.88
TOTAL ENERGY COSTS $1,917,341
RECOMMENDED SAVINGS* $247,300 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $104,341
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$116,318
Cost:
$187,782
- - - - $116,318 23,836 - - -
-
kWh
-
-
kW-months/year
$116,318
23,836
MMBtu
-
-
$
02: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$52,531
Cost:
$65,527
$52,531 750,456 - - - - - - $52,531
750,456
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$5,048
Cost:
$6,145
$5,048 72,116 - - - - - - $5,048
72,116
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
04: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,656
Cost:
$11,978
$1,656 23,658 - - - - - - $1,656
23,658
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,469
Cost:
$7,737
$1,469 20,987 - - - - - - $1,469
20,987
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$14,231
Cost:
$64,515
$14,231 203,302 - - - - - - $14,231
203,302
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
07: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$19,954
Cost:
$13,110
- - $19,954 3,093 - - - - -
-
kWh
$19,954
3,093
kW-months/year
-
-
MMBtu
-
-
$
08: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$6,672
Cost:
$990
$6,672 95,314 - - - - - - $6,672
95,314
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
09: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,037
Cost:
$190
- - - - $1,037 212 - - -
-
kWh
-
-
kW-months/year
$1,037
212
MMBtu
-
-
$
10: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$19,937
Cost:
$8,250
- - - - $19,937 4,086 - - -
-
kWh
-
-
kW-months/year
$19,937
4,086
MMBtu
-
-
$
11: 3.1191 CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS Savings:
$8,447
Cost:
$25,472
- - - - - - $8,447 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$8,447
-
$
TOTAL RECOMMENDED Savings:
$247,300
Cost:
$391,696
$81,607 1,165,833 $19,954 3,093 $137,292 28,134 $8,447 - $81,607
1,165,833
kWh
$19,954
3,093
kW-months/year
$137,292
28,134
MMBtu
$8,447
-
$
TOTAL IMPLEMENTED Savings:
$104,341
Cost:
$177,541
$74,903 1,070,059 $19,954 3,093 $1,037 212 $8,447 - $74,903
1,070,059
kWh
$19,954
3,093
kW-months/year
$1,037
212
MMBtu
$8,447
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost Electricity Usage Electricity Demand Natural Gas One-time Revenue or Avoided Cost