IAC Assessment: OK0928
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OK0928
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oklahoma State University
Assessment Year 2015
Principal Product Business forms
NAICS 323111 - Commercial Printing (except Screen and Books)
SIC 2761 - Manifold Business Forms
Sales $5,000,000-$10,000,000
# of Employees 73
Plant Area (Sq.Ft.) 110,000
Annual Production 10,800 Units
Production Hrs. Annual 6,240
Location (State) OK
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $198,366 3,641,800 kWh $0.05
Electricity Demand $60,620 8,514 kW-months/year $7.12
Natural Gas $15,678 3,528 MMBtu $4.44
TOTAL ENERGY COSTS $274,664
RECOMMENDED SAVINGS* $113,123 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $92,878
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas
$ kWh $ kW-months/year $ $ $ MMBtu
01: 2.7241 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT Savings:
$21,773
Cost:
$7,320
$21,773 403,200 - - - - - - $21,773
403,200
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
02: 2.6232 INSTALL SET-BACK TIMERS Savings:
$2,950
Cost:
$972
$2,223 41,170 - - - - $727 164 $2,223
41,170
kWh
-
-
kW-months/year
-
-
$
$727
164
MMBtu
03: 2.7211 CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS Savings:
$149
Cost:
$132
$103 1,889 $46 6 - - - - $103
1,889
kWh
$46
6
kW-months/year
-
-
$
-
-
MMBtu
04: 2.7496 INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE Savings:
$9,143
Cost:
$18,884
$7,028 130,153 - - - - $2,115 467 $7,028
130,153
kWh
-
-
kW-months/year
-
-
$
$2,115
467
MMBtu
05: 2.2437 RECOVER WASTE HEAT FROM EQUIPMENT Savings:
$988
Cost:
$2,440
- - - - - - $988 222 -
-
kWh
-
-
kW-months/year
-
-
$
$988
222
MMBtu
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$10,832
Cost:
$38,110
$9,174 169,882 $1,658 233 - - - - $9,174
169,882
kWh
$1,658
233
kW-months/year
-
-
$
-
-
MMBtu
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$18,758
Cost:
$25,753
$16,015 296,570 $2,743 385 - - - - $16,015
296,570
kWh
$2,743
385
kW-months/year
-
-
$
-
-
MMBtu
08: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,204
Cost:
$5,149
$1,204 22,304 - - - - - - $1,204
22,304
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
09: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$2,212
Cost:
$863
$2,212 40,978 - - - - - - $2,212
40,978
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
10: 2.4131 SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY Savings:
$6,912
Cost:
$5,775
$6,912 128,013 - - - - - - $6,912
128,013
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
11: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$35,000
Cost:
$70,000
- - - - $35,000 - - - -
-
kWh
-
-
kW-months/year
$35,000
-
$
-
-
MMBtu
12: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$2,621
Cost:
$20,000
- - - - $2,621 - - - -
-
kWh
-
-
kW-months/year
$2,621
-
$
-
-
MMBtu
13: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$581
Cost:
$468
$581 10,764 - - - - - - $581
10,764
kWh
-
-
kW-months/year
-
-
$
-
-
MMBtu
TOTAL RECOMMENDED Savings:
$113,123
Cost:
$195,866
$67,225 1,244,923 $4,447 624 $37,621 - $3,830 853 $67,225
1,244,923
kWh
$4,447
624
kW-months/year
$37,621
-
$
$3,830
853
MMBtu
TOTAL IMPLEMENTED Savings:
$92,878
Cost:
$148,299
$52,704 975,993 $4,447 624 $35,000 - $727 164 $52,704
975,993
kWh
$4,447
624
kW-months/year
$35,000
-
$
$727
164
MMBtu
Savings
Cost
$ kWh $ kW-months/year $ $ $ MMBtu
Electricity Usage Electricity Demand Electricity Fees Natural Gas Electricity Usage Electricity Demand Electricity Fees Natural Gas