Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oklahoma State University |
---|---|
Assessment Year | 2019 |
Principal Product | Ice cream and frozen dessert |
NAICS | 311520 - Ice Cream and Frozen Dessert Manufacturing |
SIC | 2024 - Ice Cream And Frozen Desserts |
Sales | $100,000,000-$500,000,000 |
# of Employees | 249 |
Plant Area (Sq.Ft.) | 141,803 |
Annual Production | 12,400,000 Units |
Production Hrs. Annual | 6,600 |
Location (State) | OK |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $615,484 | 14,080,500 | kWh | $0.04 |
Electricity Demand | $261,772 | 33,010 | kW-months/year | $7.93 |
Electricity Fees | $3,360 | - | $ | - |
Natural Gas | $149,763 | 50,575 | MMBtu | $2.96 |
TOTAL ENERGY COSTS | $1,054,152 | |||
RECOMMENDED SAVINGS* | $46,227 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $9,843 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED |
Savings: $27,210 Cost: $730 |
$27,210 | 618,399 | - | - | - | - | - | - | - | - |
$27,210 618,399 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $5,028 Cost: $28,358 |
$3,791 | 86,150 | $1,237 | 156 | - | - | - | - | - | - |
$3,791 86,150 kWh |
$1,237 156 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $6,766 Cost: $9,480 |
$6,766 | 153,781 | - | - | - | - | - | - | - | - |
$6,766 153,781 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $4,330 Cost: - |
$4,330 | 98,410 | - | - | - | - | - | - | - | - |
$4,330 98,410 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS |
Savings: $1,523 Cost: - |
- | - | $1,523 | 192 | - | - | - | - | - | - |
- - kWh |
$1,523 192 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2441 PREHEAT BOILER MAKEUP WATER WITH WASTE PROCESS HEAT |
Savings: $885 Cost: $4,860 |
- | - | - | - | $734 | 248 | $89 | 1,589 | $62 | 2 |
- - kWh |
- - kW-months/year |
$734 248 MMBtu |
$89 1,589 Tgal |
$62 2 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.1131 REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC |
Savings: $485 Cost: $636 |
$485 | 11,025 | - | - | - | - | - | - | - | - |
$485 11,025 kWh |
- - kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $46,227 Cost: $44,064 |
$42,582 | 967,765 | $2,760 | 348 | $734 | 248 | $89 | 1,589 | $62 | 2 | $42,582 967,765 kWh |
$2,760 348 kW-months/year |
$734 248 MMBtu |
$89 1,589 Tgal |
$62 2 Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $9,843 Cost: $28,994 |
$8,606 | 195,585 | $1,237 | 156 | - | - | - | - | - | - | $8,606 195,585 kWh |
$1,237 156 kW-months/year |
- - MMBtu |
- - Tgal |
- - Tgal |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | Tgal | $ | Tgal | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal | Electricity Usage | Electricity Demand | Natural Gas | Water Usage | Water Disposal |