IAC Assessment: OR0028
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0028
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1988
Principal Product PACKAGED SEAFOOD
NAICS n/a
SIC 2092 - Fresh Or Frozen Prepared Fish
Sales $1,000,000-$5,000,000
# of Employees 80
Plant Area (Sq.Ft.) 0
Annual Production 10,500,000 Pounds
Production Hrs. Annual 8,736
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $102,243 2,227,140 kWh $0.05
TOTAL ENERGY COSTS $102,243
RECOMMENDED SAVINGS* $14,713 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $14,597
#|Description Savings
Cost
Status Electricity Usage Administrative Changes Electricity Usage Administrative Changes
$ kWh $ $
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$1,452
Cost:
$87
$1,452 31,653 - - $1,452
31,653
kWh
-
-
$
02: 3.4156 USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE Savings:
$867
Cost:
$87
- - $867 - -
-
kWh
$867
-
$
03: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$9,789
Cost:
$5,000
$9,789 212,778 - - $9,789
212,778
kWh
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$257
Cost:
$243
$257 5,569 - - $257
5,569
kWh
-
-
$
05: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$362
Cost:
$329
$362 7,913 - - $362
7,913
kWh
-
-
$
06: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE Savings:
$116
Cost:
$154
- - $116 - -
-
kWh
$116
-
$
07: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$741
Cost:
$1,192
$622 13,482 $119 - $622
13,482
kWh
$119
-
$
08: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$1,129
Cost:
$2,550
$1,129 - - - $1,129
-
kWh
-
-
$
TOTAL RECOMMENDED Savings:
$14,713
Cost:
$9,642
$13,611 271,395 $1,102 - $13,611
271,395
kWh
$1,102
-
$
TOTAL IMPLEMENTED Savings:
$14,597
Cost:
$9,488
$13,611 271,395 $986 - $13,611
271,395
kWh
$986
-
$
Savings
Cost
$ kWh $ $
Electricity Usage Administrative Changes Electricity Usage Administrative Changes