IAC logo
IAC Assessment: OR0043
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0043
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1988
Principal Product POTATO FLAKES & STARCH
NAICS n/a
SIC 2034 - Dehydrated Fruits, Vegetables, Soups
Sales $5,000,000-$10,000,000
# of Employees 100
Plant Area (Sq.Ft.) 0
Annual Production 24,000,000 Pounds
Production Hrs. Annual 6,552
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $182,468 2,920,574 kWh $0.06
LPG $210,439 53,626 MMBtu $3.92
Fuel Oil #4 $118,728 47,382 MMBtu $2.51
TOTAL ENERGY COSTS $511,635
RECOMMENDED SAVINGS* $11,712 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $6,045
#|Description Savings
Cost
Status Electricity Usage LPG Fuel Oil #4 Electricity Usage LPG Fuel Oil #4
$ kWh $ MMBtu $ MMBtu
01: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE Savings:
$506
Cost:
-
- - $324 83 $182 73 -
-
kWh
$324
83
MMBtu
$182
73
MMBtu
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$471
Cost:
$258
$471 7,620 - - - - $471
7,620
kWh
-
-
MMBtu
-
-
MMBtu
03: 2.2511 INSULATE BARE EQUIPMENT Savings:
$1,171
Cost:
$627
- - $749 191 $422 169 -
-
kWh
$749
191
MMBtu
$422
169
MMBtu
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$1,477
Cost:
$1,900
- - $947 242 $530 213 -
-
kWh
$947
242
MMBtu
$530
213
MMBtu
05: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$433
Cost:
$908
- - $277 71 $156 62 -
-
kWh
$277
71
MMBtu
$156
62
MMBtu
06: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$2,458
Cost:
$5,400
$2,458 - - - - - $2,458
-
kWh
-
-
MMBtu
-
-
MMBtu
07: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$5,196
Cost:
$12,635
- - $3,324 848 $1,872 749 -
-
kWh
$3,324
848
MMBtu
$1,872
749
MMBtu
TOTAL RECOMMENDED Savings:
$11,712
Cost:
$21,728
$2,929 7,620 $5,621 1,435 $3,162 1,266 $2,929
7,620
kWh
$5,621
1,435
MMBtu
$3,162
1,266
MMBtu
TOTAL IMPLEMENTED Savings:
$6,045
Cost:
$8,835
$2,458 - $2,297 587 $1,290 517 $2,458
-
kWh
$2,297
587
MMBtu
$1,290
517
MMBtu
Savings
Cost
$ kWh $ MMBtu $ MMBtu
Electricity Usage LPG Fuel Oil #4 Electricity Usage LPG Fuel Oil #4