Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1988 |
Principal Product | POTATO FLAKES & STARCH |
NAICS | n/a |
SIC | 2034 - Dehydrated Fruits, Vegetables, Soups |
Sales | $5,000,000-$10,000,000 |
# of Employees | 100 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 24,000,000 Pounds |
Production Hrs. Annual | 6,552 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $182,468 | 2,920,574 | kWh | $0.06 |
LPG | $210,439 | 53,626 | MMBtu | $3.92 |
Fuel Oil #4 | $118,728 | 47,382 | MMBtu | $2.51 |
TOTAL ENERGY COSTS | $511,635 | |||
RECOMMENDED SAVINGS* | $11,712 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $6,045 |
#|Description |
Savings Cost |
Status | Electricity Usage | LPG | Fuel Oil #4 | Electricity Usage | LPG | Fuel Oil #4 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | MMBtu | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2163 USE MINIMUM STEAM OPERATING PRESSURE |
Savings: $506 Cost: - |
- | - | $324 | 83 | $182 | 73 |
- - kWh |
$324 83 MMBtu |
$182 73 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $471 Cost: $258 |
$471 | 7,620 | - | - | - | - |
$471 7,620 kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2511 INSULATE BARE EQUIPMENT |
Savings: $1,171 Cost: $627 |
- | - | $749 | 191 | $422 | 169 |
- - kWh |
$749 191 MMBtu |
$422 169 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES |
Savings: $1,477 Cost: $1,900 |
- | - | $947 | 242 | $530 | 213 |
- - kWh |
$947 242 MMBtu |
$530 213 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES |
Savings: $433 Cost: $908 |
- | - | $277 | 71 | $156 | 62 |
- - kWh |
$277 71 MMBtu |
$156 62 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,458 Cost: $5,400 |
$2,458 | - | - | - | - | - |
$2,458 - kWh |
- - MMBtu |
- - MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $5,196 Cost: $12,635 |
- | - | $3,324 | 848 | $1,872 | 749 |
- - kWh |
$3,324 848 MMBtu |
$1,872 749 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $11,712 Cost: $21,728 |
$2,929 | 7,620 | $5,621 | 1,435 | $3,162 | 1,266 | $2,929 7,620 kWh |
$5,621 1,435 MMBtu |
$3,162 1,266 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $6,045 Cost: $8,835 |
$2,458 | - | $2,297 | 587 | $1,290 | 517 | $2,458 - kWh |
$2,297 587 MMBtu |
$1,290 517 MMBtu |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | MMBtu | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | LPG | Fuel Oil #4 | Electricity Usage | LPG | Fuel Oil #4 |