Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1991 |
Principal Product | WALL PANELING |
NAICS | n/a |
SIC | 2435 - Hardwood Veneer And Plywood |
Sales | $1,000,000-$5,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 17 Thousand Feet |
Production Hrs. Annual | 2,000 |
Location (State) | WA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $22,073 | 430,246 | kWh | $0.05 |
Natural Gas | $19,191 | 4,147 | MMBtu | $4.63 |
TOTAL ENERGY COSTS | $41,264 | |||
RECOMMENDED SAVINGS* | $24,876 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $24,876 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $2,687 Cost: $4,200 |
$2,687 | 71,512 | - | - | - | - |
$2,687 71,512 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $3,011 Cost: $4,800 |
$3,011 | - | - | - | - | - |
$3,011 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $2,873 Cost: - |
$1,464 | 38,980 | - | - | $1,409 | - |
$1,464 38,980 kWh |
- - MMBtu |
$1,409 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $181 Cost: $691 |
$181 | 4,982 | - | - | - | - |
$181 4,982 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.1321 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT |
Savings: $16,124 Cost: - |
$(-3,067) | (-57,737) | $19,191 | 4,147 | - | - |
$(-3,067) (-57,737) kWh |
$19,191 4,147 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $24,876 Cost: $9,691 |
$4,276 | 57,737 | $19,191 | 4,147 | $1,409 | - | $4,276 57,737 kWh |
$19,191 4,147 MMBtu |
$1,409 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $24,876 Cost: $9,691 |
$4,276 | 57,737 | $19,191 | 4,147 | $1,409 | - | $4,276 57,737 kWh |
$19,191 4,147 MMBtu |
$1,409 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |