IAC Assessment: OR0152
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0152
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1992
Principal Product DIMENSIONAL LUMBER
NAICS n/a
SIC 2421 - Sawmills And Planing Mills, General
Sales $10,000,000-$50,000,000
# of Employees 115
Plant Area (Sq.Ft.) 0
Annual Production 65,000 Thousand Feet
Production Hrs. Annual 2,000
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,132,628 27,406,800 kWh $0.04
Wood $601,425 7,993,021 MMBtu $0.08
TOTAL ENERGY COSTS $1,734,053
RECOMMENDED SAVINGS* $156,380 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $44,472
#|Description Savings
Cost
Status Electricity Usage Administrative Changes Electricity Usage Administrative Changes
$ kWh $ $
01: 2.7111 REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS Savings:
$993
Cost:
$711
$848 17,878 $145 - $848
17,878
kWh
$145
-
$
02: 2.6232 INSTALL SET-BACK TIMERS Savings:
$26,976
Cost:
$20,752
$21,981 594,080 $4,995 - $21,981
594,080
kWh
$4,995
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$15,045
Cost:
$17,766
$12,488 264,068 $2,557 - $12,488
264,068
kWh
$2,557
-
$
04: 2.3411 REPLACE ELECTRIC MOTORS WITH BACK PRESSURE STEAM TURBINES AND USE EXHAUST STEAM FOR PROCESS HEAT Savings:
$27,941
Cost:
$49,500
$27,941 804,220 - - $27,941
804,220
kWh
-
-
$
05: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,458
Cost:
$2,813
$1,458 31,946 - - $1,458
31,946
kWh
-
-
$
06: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$83,967
Cost:
$300,000
$83,967 1,823,857 - - $83,967
1,823,857
kWh
-
-
$
TOTAL RECOMMENDED Savings:
$156,380
Cost:
$391,542
$148,683 3,536,049 $7,697 - $148,683
3,536,049
kWh
$7,697
-
$
TOTAL IMPLEMENTED Savings:
$44,472
Cost:
$42,042
$36,775 907,972 $7,697 - $36,775
907,972
kWh
$7,697
-
$
Savings
Cost
$ kWh $ $
Electricity Usage Administrative Changes Electricity Usage Administrative Changes