IAC Assessment: OR0176
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0176
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1993
Principal Product Glass Fiber
NAICS n/a
SIC 3296 - Mineral Wool
Sales $10,000,000-$50,000,000
# of Employees 117
Plant Area (Sq.Ft.) 0
Annual Production 12,000,000 Pounds
Production Hrs. Annual 8,736
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $1,176,719 32,131,302 kWh $0.04
Natural Gas $530,947 392,858 MMBtu $1.35
TOTAL ENERGY COSTS $1,707,666
RECOMMENDED SAVINGS* $30,582 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $4,334
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Electricity Usage Natural Gas Personnel Changes
$ kWh $ MMBtu $ $
01: 2.2511 INSULATE BARE EQUIPMENT Savings:
$576
Cost:
-
- - $576 426 - - -
-
kWh
$576
426
MMBtu
-
-
$
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT Savings:
$11,144
Cost:
$23,450
- - $11,144 8,246 - - -
-
kWh
$11,144
8,246
MMBtu
-
-
$
03: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$270
Cost:
-
$270 7,034 - - - - $270
7,034
kWh
-
-
MMBtu
-
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,776
Cost:
$2,859
$1,776 47,479 - - - - $1,776
47,479
kWh
-
-
MMBtu
-
-
$
05: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$5,174
Cost:
$9,100
$5,174 139,801 - - - - $5,174
139,801
kWh
-
-
MMBtu
-
-
$
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$1,712
Cost:
$2,537
$1,935 52,462 - - $(-223) - $1,935
52,462
kWh
-
-
MMBtu
$(-223)
-
$
07: 2.3212 OPTIMIZE PLANT POWER FACTOR Savings:
$9,930
Cost:
$21,000
$9,930 - - - - - $9,930
-
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$30,582
Cost:
$58,946
$19,085 246,776 $11,720 8,672 $(-223) - $19,085
246,776
kWh
$11,720
8,672
MMBtu
$(-223)
-
$
TOTAL IMPLEMENTED Savings:
$4,334
Cost:
$5,396
$3,981 106,975 $576 426 $(-223) - $3,981
106,975
kWh
$576
426
MMBtu
$(-223)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Personnel Changes Electricity Usage Natural Gas Personnel Changes