IAC Assessment: OR0184
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0184
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 1993
Principal Product Fruit Juice Concentrate
NAICS n/a
SIC 2033 - Canned Fruits And Vegetables
Sales $50,000,000-$100,000,000
# of Employees 100
Plant Area (Sq.Ft.) 0
Annual Production 65,000,000 Pounds
Production Hrs. Annual 7,368
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $150,626 3,079,719 kWh $0.05
Natural Gas $171,109 65,234 MMBtu $2.62
TOTAL ENERGY COSTS $321,735
RECOMMENDED SAVINGS* $9,712 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,130
#|Description Savings
Cost
Status Electricity Usage Natural Gas Personnel Changes Electricity Usage Natural Gas Personnel Changes
$ kWh $ MMBtu $ $
01: 2.1232 KEEP BOILER TUBES CLEAN Savings:
$3,632
Cost:
$500
- - $4,632 1,768 $(-1,000) - -
-
kWh
$4,632
1,768
MMBtu
$(-1,000)
-
$
02: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$5,103
Cost:
$2,385
- - $5,103 1,948 - - -
-
kWh
$5,103
1,948
MMBtu
-
-
$
03: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$582
Cost:
$1,229
$632 14,068 - - $(-50) - $632
14,068
kWh
-
-
MMBtu
$(-50)
-
$
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$395
Cost:
$1,090
$395 7,913 - - - - $395
7,913
kWh
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$9,712
Cost:
$5,204
$1,027 21,981 $9,735 3,716 $(-1,050) - $1,027
21,981
kWh
$9,735
3,716
MMBtu
$(-1,050)
-
$
TOTAL IMPLEMENTED Savings:
$9,130
Cost:
$3,975
$395 7,913 $9,735 3,716 $(-1,000) - $395
7,913
kWh
$9,735
3,716
MMBtu
$(-1,000)
-
$
Savings
Cost
$ kWh $ MMBtu $ $
Electricity Usage Natural Gas Personnel Changes Electricity Usage Natural Gas Personnel Changes