Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 1997 |
Principal Product | Milk, Ice Cream, Cottage Cheese |
NAICS | n/a |
SIC | 2026 - Fluid Milk |
Sales | $10,000,000-$50,000,000 |
# of Employees | 120 |
Plant Area (Sq.Ft.) | 85,236 |
Annual Production | 164,989,620 Pounds |
Production Hrs. Annual | 3,536 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $360,454 | 10,989,156 | kWh | $0.03 |
Electricity Demand | $91,660 | 515,124 | kW-months/year | $0.18 |
Electricity Fees | $27,638 | - | $ | - |
Natural Gas | $72,106 | 26,581 | MMBtu | $2.71 |
TOTAL ENERGY COSTS | $678,222 | |||
RECOMMENDED SAVINGS* | $432,773 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $148,901 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 3.4151 MINIMIZE WATER USAGE |
Savings: $277,700 Cost: $336,500 |
$(-10,900) | (-332,943) | $(-6,400) | (-1,464) | - | - | - | - | $295,000 | - | - | 732,000 | - | - | - | - |
$(-10,900) (-332,943) kWh |
$(-6,400) (-1,464) kW-months/year |
- - $ |
- - MMBtu |
$295,000 - Tgal |
- 732,000 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $2,215 Cost: - |
- | - | - | - | - | - | - | - | - | - | $2,215 | 29,614 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
$2,215 29,614 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $1,880 Cost: - |
- | - | - | - | - | - | - | - | - | - | $1,880 | 26,520 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
$1,880 26,520 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 3.5311 RECOVER AND REUSE WASTE MATERIAL |
Savings: $1,275 Cost: - |
- | - | - | - | - | - | - | - | - | - | $1,275 | 10,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
$1,275 10,000 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2611 MODERATE COOLING TOWER OUTLET TEMPERATURE |
Savings: $34,550 Cost: $24,000 |
$42,550 | 1,297,186 | - | - | - | - | - | - | - | - | - | - | - | - | $(-8,000) | - |
$42,550 1,297,186 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
$(-8,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.2611 MODERATE COOLING TOWER OUTLET TEMPERATURE |
Savings: $5,800 Cost: - |
$5,800 | 177,022 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$5,800 177,022 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.2611 MODERATE COOLING TOWER OUTLET TEMPERATURE |
Savings: $24,530 Cost: $7,000 |
$24,530 | 747,948 | - | - | - | - | - | - | - | - | - | - | - | - | - | - |
$24,530 747,948 kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS |
Savings: $8,751 Cost: $20,994 |
$6,566 | 200,176 | $2,185 | 502 | - | - | - | - | - | - | - | - | - | - | - | - |
$6,566 200,176 kWh |
$2,185 502 kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2121 INCREASE AMOUNT OF CONDENSATE RETURNED |
Savings: $6,850 Cost: $4,200 |
- | - | - | - | - | - | $6,850 | 2,793 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
$6,850 2,793 MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.3212 OPTIMIZE PLANT POWER FACTOR |
Savings: $2,682 Cost: $18,000 |
- | - | - | - | $2,682 | - | - | - | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,682 - $ |
- - MMBtu |
- - Tgal |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 4.311 SCHEDULE DELIVERIES ACCORDING TO DEMAND |
Savings: $4,240 Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | $4,240 | - | - | - |
- - kWh |
- - kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
$4,240 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 4.311 SCHEDULE DELIVERIES ACCORDING TO DEMAND |
Savings: $62,300 Cost: $51,600 |
$(-125) | (-3,810) | $(-220) | (-48) | - | - | - | - | - | - | - | - | $62,645 | - | - | - |
$(-125) (-3,810) kWh |
$(-220) (-48) kW-months/year |
- - $ |
- - MMBtu |
- - Tgal |
- - lb |
$62,645 - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $432,773 Cost: $462,294 |
$68,421 | 2,085,579 | $(-4,435) | (-1,010) | $2,682 | - | $6,850 | 2,793 | $295,000 | - | $5,370 | 798,134 | $66,885 | - | $(-8,000) | - | $68,421 2,085,579 kWh |
$(-4,435) (-1,010) kW-months/year |
$2,682 - $ |
$6,850 2,793 MMBtu |
$295,000 - Tgal |
$5,370 798,134 lb |
$66,885 - $ |
$(-8,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $148,901 Cost: $107,794 |
$79,321 | 2,418,522 | $1,965 | 454 | - | - | $6,850 | 2,793 | - | - | $1,880 | 26,520 | $66,885 | - | $(-8,000) | - | $79,321 2,418,522 kWh |
$1,965 454 kW-months/year |
- - $ |
$6,850 2,793 MMBtu |
- - Tgal |
$1,880 26,520 lb |
$66,885 - $ |
$(-8,000) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | $ | $ | MMBtu | $ | Tgal | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Electricity Fees | Natural Gas | Water Disposal | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |