IAC logo
IAC Assessment: OR0504
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0504
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2006
Principal Product Fibercement siding
NAICS 327390 - Other Concrete Product Manufacturing
SIC 3272 - Concrete Products, Nec
Sales $50,000,000-$100,000,000
# of Employees 88
Plant Area (Sq.Ft.) 145,000
Annual Production 120,000 Thousand Feet
Production Hrs. Annual 8,400
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $688,460 20,088,000 kWh $0.03
Electricity Demand $161,872 3,190 kW-months/year $50.74
Electricity Fees $36,412 - $ -
Natural Gas $1,313,458 125,047 MMBtu $10.50
TOTAL ENERGY COSTS $2,200,202
RECOMMENDED SAVINGS* $230,500 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $109,800
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes
$ kWh $ kW-months/year $ MMBtu $ $
01: 2.2449 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER Savings:
$64,300
Cost:
$20,000
- - - - $64,300 4,090 - - -
-
kWh
-
-
kW-months/year
$64,300
4,090
MMBtu
-
-
$
02: 2.1394 REPLACE STEAM JETS ON VACUUM SYSTEM WITH ELECTRIC MOTOR DRIVEN VACUUM PUMPS Savings:
$22,500
Cost:
$44,500
$(-3,400) (-95,400) $(-1,400) (-28) $27,300 2,600 - - $(-3,400)
(-95,400)
kWh
$(-1,400)
(-28)
kW-months/year
$27,300
2,600
MMBtu
-
-
$
03: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$84,100
Cost:
-
- - - - - - $84,100 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$84,100
-
$
04: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL Savings:
$28,000
Cost:
-
- - - - - - $28,000 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$28,000
-
$
05: 2.6242 MINIMIZE OPERATION OF EQUIPMENT MAINTAINED IN STANDBY CONDITION Savings:
$23,000
Cost:
-
$23,000 650,800 - - - - - - $23,000
650,800
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
06: 2.5194 REDESIGN PROCESS Savings:
$6,100
Cost:
$5,000
$5,200 152,400 $900 17 - - - - $5,200
152,400
kWh
$900
17
kW-months/year
-
-
MMBtu
-
-
$
07: 2.6212 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME Savings:
$2,500
Cost:
$1,000
$2,500 70,000 - - - - - - $2,500
70,000
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
TOTAL RECOMMENDED Savings:
$230,500
Cost:
$70,500
$27,300 777,800 $(-500) (-11) $91,600 6,690 $112,100 - $27,300
777,800
kWh
$(-500)
(-11)
kW-months/year
$91,600
6,690
MMBtu
$112,100
-
$
TOTAL IMPLEMENTED Savings:
$109,800
Cost:
$64,500
$19,600 555,400 $(-1,400) (-28) $91,600 6,690 - - $19,600
555,400
kWh
$(-1,400)
(-28)
kW-months/year
$91,600
6,690
MMBtu
-
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Electricity Usage Electricity Demand Natural Gas Administrative Changes