IAC Assessment: OR0621
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: OR0621
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Oregon State University
Assessment Year 2013
Principal Product Sulfur
NAICS 212393 - Other Chemical and Fertilizer Mineral Mining
SIC 1479 - Chemical And Fertilizer Mining, Nec
Sales $10,000,000-$50,000,000
# of Employees 10
Plant Area (Sq.Ft.) 287,469
Annual Production 84,000 Units
Production Hrs. Annual 4,940
Location (State) WA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $49,139 667,840 kWh $0.07
Electricity Demand $8,706 1,750 kW-months/year $4.97
Electricity Fees $620 - $ -
Natural Gas $79,350 12,341 MMBtu $6.43
Fuel Oil #2 $8,475 346 MMBtu $24.49
TOTAL ENERGY COSTS $146,290
RECOMMENDED SAVINGS* $12,150 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $9,765
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
01: 2.1116 IMPROVE COMBUSTION CONTROL CAPABILITY Savings:
$1,962
Cost:
$2,256
- - - - $1,962 308 - - - - -
-
kWh
-
-
kW-months/year
$1,962
308
MMBtu
-
-
$
-
-
$
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$9,765
Cost:
$65,592
$6,542 82,318 $1,190 158 - - $203 - $1,830 - $6,542
82,318
kWh
$1,190
158
kW-months/year
-
-
MMBtu
$203
-
$
$1,830
-
$
03: 2.4324 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT Savings:
$423
Cost:
$13,505
$423 5,714 - - - - - - - - $423
5,714
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
$
-
-
$
TOTAL RECOMMENDED Savings:
$12,150
Cost:
$81,353
$6,965 88,032 $1,190 158 $1,962 308 $203 - $1,830 - $6,965
88,032
kWh
$1,190
158
kW-months/year
$1,962
308
MMBtu
$203
-
$
$1,830
-
$
TOTAL IMPLEMENTED Savings:
$9,765
Cost:
$65,592
$6,542 82,318 $1,190 158 - - $203 - $1,830 - $6,542
82,318
kWh
$1,190
158
kW-months/year
-
-
MMBtu
$203
-
$
$1,830
-
$
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ $ $ $
Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost Electricity Usage Electricity Demand Natural Gas Administrative Changes Ancillary Material Cost