Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | Oregon State University |
---|---|
Assessment Year | 2021 |
Principal Product | Semiconductor Products and Contract Manufacturing |
NAICS | 334413 - Semiconductor and Related Device Manufacturing |
SIC | 3674 - Semiconductors And Related Devices |
Sales | $100,000,000-$500,000,000 |
# of Employees | 300 |
Plant Area (Sq.Ft.) | 170,000 |
Annual Production | 20,000 Units |
Production Hrs. Annual | 2,800 |
Location (State) | OR |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $182,254 | 3,122,138 | kWh | $0.06 |
Electricity Demand | $46,933 | 7,097 | kW-months/year | $6.61 |
Electricity Fees | $63,157 | - | $ | - |
Natural Gas | $30,875 | 3,442 | MMBtu | $8.97 |
TOTAL ENERGY COSTS | $367,879 | |||
RECOMMENDED SAVINGS* | $98,069 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | - |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $16,176 Cost: $40,448 |
$11,499 | 159,861 | $3,962 | 519 | - | - | - | - | $1,150 | - | $(-435) | - |
$11,499 159,861 kWh |
$3,962 519 kW-months/year |
- - MMBtu |
- - lb |
$1,150 - $ |
$(-435) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 3.6192 USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL |
Savings: $56,371 Cost: - |
- | - | - | - | - | - | $56,371 | 812,000 | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$56,371 812,000 lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.7234 USE HEAT PUMP FOR SPACE CONDITIONING |
Savings: $25,522 Cost: $19,860 |
$18,301 | 254,430 | $16,502 | 2,160 | $(-9,281) | (-1,035) | - | - | - | - | - | - |
$18,301 254,430 kWh |
$16,502 2,160 kW-months/year |
$(-9,281) (-1,035) MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $98,069 Cost: $60,308 |
$29,800 | 414,291 | $20,464 | 2,679 | $(-9,281) | (-1,035) | $56,371 | 812,000 | $1,150 | - | $(-435) | - | $29,800 414,291 kWh |
$20,464 2,679 kW-months/year |
$(-9,281) (-1,035) MMBtu |
$56,371 812,000 lb |
$1,150 - $ |
$(-435) - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: - Cost: - |
- | - | - | - | - | - | - | - | - | - | - | - | - - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - $ |
- - $ |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Personnel Changes | Ancillary Material Cost |