Select a Center

Arizona State University
Case Western Reserve University
Colorado School of Mines
Colorado State University
Indiana University-Purdue University
Kennesaw State
Lehigh University
Louisiana State University
Louisiana Tech
Michigan State University
Mississippi State
Oklahoma State University
Oregon State University
San Francisco State University
Syracuse University
Tennessee Technological University
Texas A&M, College Station
University of Alabama
University of California, Irvine
University of Connecticut
University of Dayton
University of Delaware
University of Florida
University of Illinois, Chicago
University of Louisville
University of Massachusetts
University of Miami
University of Missouri-Columbia
University of Nebraska–Lincoln
University of North Carolina, Charlotte
University of Texas Rio Grande Valley
University of Utah
University of Washington
University of Wisconsin, Milwaukee
West Virginia University
IAC logo
IAC Assessment: OR0742
Sponsored by:
EERE AMO
IAC logo
IAC Assessment: OR0742
IAC Center Oregon State University
Assessment Year 2021
Principal Product Seafood Products
NAICS 311710 - Seafood Product Preparation and Packaging
SIC 2092 - Fresh Or Frozen Prepared Fish
Sales $5,000,000-$10,000,000
# of Employees 250
Plant Area (Sq.Ft.) 51,888
Annual Production 25,000,000 Pounds
Production Hrs. Annual 5,304
Location (State) OR
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $143,281 2,149,080 kWh $0.07
Electricity Demand $21,745 4,582 kW-months/year $4.75
Electricity Fees $18,664 - $ -
Natural Gas $13,408 1,613 MMBtu $8.31
TOTAL ENERGY COSTS $197,098
RECOMMENDED SAVINGS* $26,767 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* -
#|Description Savings
Cost
Status Electricity Usage Water Usage Personnel Changes Ancillary Material Cost Electricity Usage Water Usage Personnel Changes Ancillary Material Cost
$ kWh $ Tgal $ $ $ $
01: 2.2621 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE Savings:
$4,010
Cost:
-
$4,010 57,098 - - - - - - $4,010
57,098
kWh
-
-
Tgal
-
-
$
-
-
$
02: 2.5194 REDESIGN PROCESS Savings:
$3,895
Cost:
-
$35 493 - - $3,465 - $395 - $35
493
kWh
-
-
Tgal
$3,465
-
$
$395
-
$
03: 2.6231 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED Savings:
$8,662
Cost:
$6,857
$357 5,089 $8,305 1,755 - - - - $357
5,089
kWh
$8,305
1,755
Tgal
-
-
$
-
-
$
04: 2.3132 RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS Savings:
$10,200
Cost:
$38,018
- - - - - - $10,200 - -
-
kWh
-
-
Tgal
-
-
$
$10,200
-
$
TOTAL RECOMMENDED Savings:
$26,767
Cost:
$44,875
$4,402 62,680 $8,305 1,755 $3,465 - $10,595 - $4,402
62,680
kWh
$8,305
1,755
Tgal
$3,465
-
$
$10,595
-
$
TOTAL IMPLEMENTED Savings:
-
Cost:
-
- - - - - - - - -
-
kWh
-
-
Tgal
-
-
$
-
-
$
Savings
Cost
$ kWh $ Tgal $ $ $ $
Electricity Usage Water Usage Personnel Changes Ancillary Material Cost Electricity Usage Water Usage Personnel Changes Ancillary Material Cost