IAC Assessment: RU0109
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center Rutgers, State Univ. of NJ
Assessment Year 1991
Principal Product FASTENERS
NAICS n/a
SIC 3452 - Bolts, Nuts, Rivets, And Washers
Sales $10,000,000-$50,000,000
# of Employees 195
Plant Area (Sq.Ft.) 0
Annual Production 1,560,000,000 Pieces
Production Hrs. Annual 6,000
Location (State) NJ
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $189,460 2,292,497 kWh $0.08
Natural Gas $20,364 3,282 MMBtu $6.20
TOTAL ENERGY COSTS $209,824
RECOMMENDED SAVINGS* $18,125 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $18,125
#|Description Savings
Cost
Status Electricity Usage Natural Gas Electricity Usage Natural Gas
$ kWh $ MMBtu
01: 2.4111 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS Savings:
$2,147
Cost:
-
$2,147 25,791 - - $2,147
25,791
kWh
-
-
MMBtu
02: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS Savings:
$2,160
Cost:
$308
$2,160 26,084 - - $2,160
26,084
kWh
-
-
MMBtu
03: 2.8114 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE Savings:
$2,849
Cost:
$2,500
- - $2,849 - -
-
kWh
$2,849
-
MMBtu
04: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES Savings:
$851
Cost:
$300
$851 10,258 - - $851
10,258
kWh
-
-
MMBtu
05: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED Savings:
$4,456
Cost:
-
$4,456 53,634 - - $4,456
53,634
kWh
-
-
MMBtu
06: 2.4221 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS Savings:
$2,570
Cost:
$166
$2,570 31,067 - - $2,570
31,067
kWh
-
-
MMBtu
07: 2.2122 INSTALL / REPAIR INSULATION ON CONDENSATE LINES Savings:
$88
Cost:
$28
- - $88 14 -
-
kWh
$88
14
MMBtu
08: 2.2136 INSTALL / REPAIR INSULATION ON STEAM LINES Savings:
$374
Cost:
$180
- - $374 58 -
-
kWh
$374
58
MMBtu
09: 2.1233 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO Savings:
$509
Cost:
$500
- - $509 82 -
-
kWh
$509
82
MMBtu
10: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT Savings:
$2,121
Cost:
-
$3,113 37,515 $(-992) (-160) $3,113
37,515
kWh
$(-992)
(-160)
MMBtu
TOTAL RECOMMENDED Savings:
$18,125
Cost:
$3,982
$15,297 184,349 $2,828 (-6) $15,297
184,349
kWh
$2,828
(-6)
MMBtu
TOTAL IMPLEMENTED Savings:
$18,125
Cost:
$3,982
$15,297 184,349 $2,828 (-6) $15,297
184,349
kWh
$2,828
(-6)
MMBtu
Savings
Cost
$ kWh $ MMBtu
Electricity Usage Natural Gas Electricity Usage Natural Gas