Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 1993 |
Principal Product | HEAT TREATING, HARDENING |
NAICS | n/a |
SIC | 3398 - Metal Heat Treating |
Sales | $1,000,000-$5,000,000 |
# of Employees | 20 |
Plant Area (Sq.Ft.) | 0 |
Annual Production | 20,000 Tons |
Production Hrs. Annual | 4,334 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $150,846 | 1,535,170 | kWh | $0.10 |
Natural Gas | $30,275 | 5,389 | MMBtu | $5.62 |
TOTAL ENERGY COSTS | $181,121 | |||
RECOMMENDED SAVINGS* | $12,284 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $4,515 |
#|Description |
Savings Cost |
Status | Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | MMBtu | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.2514 COVER OPEN TANKS |
Savings: $1,443 Cost: $85 |
- | - | $1,443 | 257 | - | - |
- - kWh |
$1,443 257 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.2414 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT |
Savings: $2,816 Cost: $10,500 |
- | - | $2,816 | 501 | - | - |
- - kWh |
$2,816 501 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.2514 COVER OPEN TANKS |
Savings: $96 Cost: $54 |
- | - | $96 | 17 | - | - |
- - kWh |
$96 17 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $748 Cost: - |
$748 | 7,620 | - | - | - | - |
$748 7,620 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.3131 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS |
Savings: $2,049 Cost: - |
$2,049 | - | - | - | - | - |
$2,049 - kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.7142 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS |
Savings: $690 Cost: $87 |
$732 | 7,327 | - | - | $(-42) | - |
$732 7,327 kWh |
- - MMBtu |
$(-42) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.7144 INSTALL SPECTRAL REFLECTORS / DELAMP |
Savings: $403 Cost: $480 |
$432 | 3,810 | - | - | $(-29) | - |
$432 3,810 kWh |
- - MMBtu |
$(-29) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.6232 INSTALL SET-BACK TIMERS |
Savings: $220 Cost: $360 |
$230 | 2,345 | - | - | $(-10) | - |
$230 2,345 kWh |
- - MMBtu |
$(-10) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.7134 USE PHOTOCELL CONTROLS |
Savings: $3,563 Cost: $2,475 |
$3,609 | 36,635 | - | - | $(-46) | - |
$3,609 36,635 kWh |
- - MMBtu |
$(-46) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.7261 INSTALL TIMERS AND/OR THERMOSTATS |
Savings: $256 Cost: $300 |
$256 | 2,638 | - | - | - | - |
$256 2,638 kWh |
- - MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $12,284 Cost: $14,341 |
$8,056 | 60,375 | $4,355 | 775 | $(-127) | - | $8,056 60,375 kWh |
$4,355 775 MMBtu |
$(-127) - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $4,515 Cost: $10,885 |
$256 | 2,638 | $4,259 | 758 | - | - | $256 2,638 kWh |
$4,259 758 MMBtu |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | MMBtu | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Natural Gas | Administrative Changes | Electricity Usage | Natural Gas | Administrative Changes |