Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center | San Diego State University |
---|---|
Assessment Year | 2003 |
Principal Product | plastic and rubber products |
NAICS | 326291 - Rubber Product Manufacturing for Mechanical Use |
SIC | 3061 - Mechanical Rubber Goods |
Sales | $50,000,000-$100,000,000 |
# of Employees | 600 |
Plant Area (Sq.Ft.) | 290,000 |
Annual Production | 500,000 Pounds |
Production Hrs. Annual | 6,000 |
Location (State) | CA |
Source | Yearly Cost | Usage | Unit | Unit Cost |
---|---|---|---|---|
Electricity Usage | $1,397,224 | 12,950,491 | kWh | $0.11 |
Electricity Demand | $412,086 | 34,564 | kW-months/year | $11.92 |
Natural Gas | $509,451 | 71,836 | MMBtu | $7.09 |
TOTAL ENERGY COSTS | $2,458,901 | |||
RECOMMENDED SAVINGS* | $639,009 | *Non-energy impacts included in savings. See recommendations below |
||
IMPLEMENTED SAVINGS* | $263,736 |
#|Description |
Savings Cost |
Status | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | Ancillary Material Cost | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | lb | $ | $ | $ | $ | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $81,424 Cost: $31,100 |
$67,919 | 629,465 | $13,505 | 1,133 | - | - | - | - | - | - | - | - | - | - |
$67,919 629,465 kWh |
$13,505 1,133 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
02: 2.1311 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT |
Savings: $70,391 Cost: $78,000 |
$48,264 | 447,300 | $36,559 | 3,067 | $(-14,432) | (-2,350) | - | - | - | - | - | - | - | - |
$48,264 447,300 kWh |
$36,559 3,067 kW-months/year |
$(-14,432) (-2,350) MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
03: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $31,150 Cost: $14,100 |
$28,051 | 259,974 | $3,099 | 260 | - | - | - | - | - | - | - | - | - | - |
$28,051 259,974 kWh |
$3,099 260 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
04: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $29,977 Cost: $1,515 |
$14,243 | 132,000 | $15,734 | 1,320 | - | - | - | - | - | - | - | - | - | - |
$14,243 132,000 kWh |
$15,734 1,320 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
05: 2.2113 REPAIR OR REPLACE STEAM TRAPS |
Savings: $22,467 Cost: $9,950 |
- | - | - | - | $22,467 | 3,168 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$22,467 3,168 MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
06: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM |
Savings: $22,675 Cost: $10,950 |
$18,575 | 172,154 | $4,100 | 344 | - | - | - | - | - | - | - | - | - | - |
$18,575 172,154 kWh |
$4,100 344 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
07: 2.4321 UPGRADE OBSOLETE EQUIPMENT |
Savings: $14,674 Cost: $160 |
$12,016 | 111,360 | $2,658 | 223 | - | - | - | - | - | - | - | - | - | - |
$12,016 111,360 kWh |
$2,658 223 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
08: 2.4231 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED |
Savings: $13,816 Cost: - |
$11,313 | 104,850 | $2,503 | 210 | - | - | - | - | - | - | - | - | - | - |
$11,313 104,850 kWh |
$2,503 210 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
09: 2.2135 REPAIR AND ELIMINATE STEAM LEAKS |
Savings: $7,163 Cost: $6,600 |
- | - | - | - | $7,163 | 1,010 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$7,163 1,010 MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
10: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $11,780 Cost: $1,550 |
$6,440 | 59,680 | $5,340 | 448 | - | - | - | - | - | - | - | - | - | - |
$6,440 59,680 kWh |
$5,340 448 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
11: 2.4236 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES |
Savings: $10,312 Cost: $240 |
$8,446 | 78,286 | $1,866 | 157 | - | - | - | - | - | - | - | - | - | - |
$8,446 78,286 kWh |
$1,866 157 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
12: 2.7145 INSTALL SKYLIGHTS |
Savings: $8,457 Cost: $23,000 |
$4,489 | 41,602 | $3,968 | 333 | - | - | - | - | - | - | - | - | - | - |
$4,489 41,602 kWh |
$3,968 333 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
13: 2.6218 TURN OFF EQUIPMENT WHEN NOT IN USE |
Savings: $3,005 Cost: $1,500 |
$1,932 | 17,904 | $1,073 | 90 | - | - | - | - | - | - | - | - | - | - |
$1,932 17,904 kWh |
$1,073 90 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
14: 2.7135 INSTALL OCCUPANCY SENSORS |
Savings: $2,734 Cost: $750 |
$898 | 8,320 | $1,836 | 154 | - | - | - | - | - | - | - | - | - | - |
$898 8,320 kWh |
$1,836 154 kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
15: 2.2153 CLOSE OFF UNNEEDED STEAM LINES |
Savings: $2,248 Cost: $1,350 |
- | - | - | - | $2,248 | 317 | - | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
$2,248 317 MMBtu |
- - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
16: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $222,070 Cost: $9,000 |
- | - | - | - | - | - | - | - | $10,070 | 212,000 | $212,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
$10,070 212,000 lb |
$212,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
17: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $52,500 Cost: $15,360 |
- | - | - | - | - | - | - | - | - | - | - | - | $52,500 | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - lb |
- - $ |
$52,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
18: 3.1192 REDUCE SCRAP PRODUCTION |
Savings: $30,000 Cost: $1,400 |
- | - | - | - | - | - | - | - | - | - | $30,000 | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
- - lb |
- - lb |
$30,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
19: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS |
Savings: $2,166 Cost: - |
- | - | - | - | - | - | $2,166 | - | - | - | - | - | - | - |
- - kWh |
- - kW-months/year |
- - MMBtu |
$2,166 - lb |
- - lb |
- - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL RECOMMENDED |
Savings: $639,009 Cost: $206,525 |
$222,586 | 2,062,895 | $92,241 | 7,739 | $17,446 | 2,145 | $2,166 | - | $10,070 | 212,000 | $242,000 | - | $52,500 | - | $222,586 2,062,895 kWh |
$92,241 7,739 kW-months/year |
$17,446 2,145 MMBtu |
$2,166 - lb |
$10,070 212,000 lb |
$242,000 - $ |
$52,500 - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
TOTAL IMPLEMENTED |
Savings: $263,736 Cost: $23,350 |
$8,372 | 77,584 | $6,413 | 538 | $24,715 | 3,485 | $2,166 | - | $10,070 | 212,000 | $212,000 | - | - | - | $8,372 77,584 kWh |
$6,413 538 kW-months/year |
$24,715 3,485 MMBtu |
$2,166 - lb |
$10,070 212,000 lb |
$212,000 - $ |
- - $ |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Savings Cost |
$ | kWh | $ | kW-months/year | $ | MMBtu | $ | lb | $ | lb | $ | $ | $ | $ | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | Ancillary Material Cost | Electricity Usage | Electricity Demand | Natural Gas | Solid Waste (non-haz) | Solid Waste (haz) | Primary Raw Material | Ancillary Material Cost |