IAC Assessment: SD0344
Sponsored by:
DOE MESC
IAC logo
IAC Assessment: SD0344
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
IAC Center San Diego State University
Assessment Year 2004
Principal Product Springs
NAICS 332613 - Spring Manufacturing
SIC 3493 - Steel Springs, Except Wire
Sales $10,000,000-$50,000,000
# of Employees 65
Plant Area (Sq.Ft.) 100,000
Annual Production 637,500 Pieces
Production Hrs. Annual 4,080
Location (State) CA
Source Yearly Cost Usage Unit Unit Cost
Electricity Usage $134,601 1,149,039 kWh $0.12
Electricity Demand $48,819 6,066 kW-months/year $8.05
Natural Gas $15,218 2,069 MMBtu $7.36
TOTAL ENERGY COSTS $198,638
RECOMMENDED SAVINGS* $64,931 *Non-energy impacts
included in savings.
See recommendations below
IMPLEMENTED SAVINGS* $49,484
#|Description Savings
Cost
Status Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)
$ kWh $ kW-months/year $ MMBtu $ lb
01: 2.4146 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM Savings:
$42,981
Cost:
$35,875
$42,981 367,049 - - - - - - $42,981
367,049
kWh
-
-
kW-months/year
-
-
MMBtu
-
-
lb
02: 2.1133 ADJUST BURNERS FOR EFFICIENT OPERATION Savings:
$6,983
Cost:
$7,700
- - - - $6,983 950 - - -
-
kWh
-
-
kW-months/year
$6,983
950
MMBtu
-
-
lb
03: 2.7141 LOWER LIGHT FIXTURES IN HIGH CEILING AREAS Savings:
$8,464
Cost:
$27,829
$6,395 54,615 $2,069 257 - - - - $6,395
54,615
kWh
$2,069
257
kW-months/year
-
-
MMBtu
-
-
lb
04: 2.4133 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS Savings:
$1,104
Cost:
$440
$74 632 $1,030 128 - - - - $74
632
kWh
$1,030
128
kW-months/year
-
-
MMBtu
-
-
lb
05: 3.6193 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS Savings:
$5,399
Cost:
$18,500
- - - - - - $5,399 - -
-
kWh
-
-
kW-months/year
-
-
MMBtu
$5,399
-
lb
TOTAL RECOMMENDED Savings:
$64,931
Cost:
$90,344
$49,450 422,296 $3,099 385 $6,983 950 $5,399 - $49,450
422,296
kWh
$3,099
385
kW-months/year
$6,983
950
MMBtu
$5,399
-
lb
TOTAL IMPLEMENTED Savings:
$49,484
Cost:
$54,815
$43,055 367,681 $1,030 128 - - $5,399 - $43,055
367,681
kWh
$1,030
128
kW-months/year
-
-
MMBtu
$5,399
-
lb
Savings
Cost
$ kWh $ kW-months/year $ MMBtu $ lb
Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz) Electricity Usage Electricity Demand Natural Gas Solid Waste (non-haz)